Description

This project provides for major roof replacement of County buildings.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$36.73M Total
Expenditures/Funding
$13.44M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Several projects will be completed during FY23 and FY24.
anchor

Cost Change

Cost increase due to the addition of expenditures in FY27 and FY28 for this ongoing project.
anchor

Justification

The age of many County buildings creates the need for this project. Factors determining the need for replacement include poor condition, age, long-term utilization, and probability of continued repairs. The project consists of an annual replacement schedule for those roofs which have reached the end of their useful service life. Asbestos abatement is an important component of the roof replacement effort and will be performed when required. The roof replacements covered under this program are prioritized based upon an in-house priority schedule. Information generated in that condition survey will be the basis for future roof replacement projects. The March 2010 Report of the Infrastructure Maintenance Task Force identified an annual level of effort funding for roof replacement based on an average 20-year life for roof systems.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Department of General Services
Budget Snapshot
$36.73M Total
Expenditures/Funding
$13.44M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP508331
Date Last Modified10/05/22
Administering AgencyGeneral Services
CategoryGeneral Government
SubCategoryCounty Offices and Other Improvements
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision92135568100526404404404404404404400
Land00000000000
Site Improvements and Utilities00000000000
Construction2614314515828108001800180018001800180018000
Other13781378000000000
Total Expenditures36734214611833134402240224022402240224022400
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds36734214611833134402240224022402240224022400
Total Funding Sources36734214611833134402240224022402240224022400
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request2240
Year First AppropriationFY96
Appropriation FY 24 Request2240
Last FY's Cost Estimate36734
Cumulative Appropriation25534
Expenditure / Encumbrances22840
Unencumbered Balance2694