up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project will renovate Johnson's Local Park, located at 18000 Washington Grove Lane in Gaithersburg, to improve recreational opportunities, strengthen community gathering spaces, and celebrate the park's cultural and historic significance. Serving a diverse surrounding population, the park supports active recreation, social connection, and neighborhood cohesion. Park improvements will enhance access to quality recreational amenities, create safer and more inclusive spaces, and reinforce the park's role as a community anchor for the Emory Grove area.
anchor

Phase

Planning Stage

Status

anchor
Budget Snapshot
$1.05M Total
Expenditures/Funding
$1.05M 6 Year Total
Expenditures/Funding
anchor

Justification

Johnson's Local Park has long been central to the historic African American community of Emory Grove, serving as a gathering place for community events, camp meetings, and historic baseball league games. Despite significant displacement during Urban Renewal efforts in the 1960s and 1970s, community advocacy preserved the park, which Montgomery Parks acquired and opened in 1974. The restoration of the park's name to Johnson's Park in 1995 reflects its continued cultural importance.
anchor

Fiscal Note

The Maryland General Assembly approved funding for Johnson's Local Park: $50,000 awarded in the FY25 Maryland Capital Budget Bill and $1,000,000 in the FY27 Maryland Capital Budget Bill.
anchor

Disclosures

M-NCPPC asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Expenditures will continue indefinitely
Download & Explore Project Details
Budget Snapshot
$1.05M Total
Expenditures/Funding
$1.05M 6 Year Total
Expenditures/Funding
anchor
Project NumberP872702
Date Last Modified05/18/26
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaGaithersburg and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision45000450450000000
Land60000600600000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures10500010501050000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
State Aid10500010501050000000
Total Funding Sources10500010501050000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request1050
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0
anchor