Description

This project involves an alignment study, design and construction of 30,200 feet of a proposed 84 inch diameter water main between the intersection of Tuckerman Lane and Route I-270 and the western terminus of the Bi-County Water Tunnel near the area where Rock Creek crosses the Capital Beltway, [Maryland Route 495].
anchor

Phase

TBA

Status

Closeout
anchor
Budget Snapshot
$141.64M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

Budget Snapshot
$141.64M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP934855
Date Last Modified10/11/18
Administering AgencyW.S.S.C.
CategoryWSSC
SubCategoryWater Bi-County
Planning AreaBi-County
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY18Est FY19Total 6 YearsFY 20FY 21FY 22FY 23FY 24FY 25Beyond 6 Years
Planning, Design and Supervision2759427594000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction113910113910000000000
Other132132000000000
Total Expenditures141636141636000000000
FUNDING (000s)
Funding SourceTotalThru FY18Est FY19Total 6 YearsFY 20FY 21FY 22FY 23FY 24FY 25Beyond 6 Years
System Development Charge140936140936000000000
WSSC Bonds700700000000000
Total Funding Sources141636141636000000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 19 Request0
Year First AppropriationFY93
Appropriation FY 20 Request0
Last FY's Cost Estimate141636
Cumulative Appropriation267208
Expenditure / Encumbrances0
Unencumbered Balance267208