Description

This project provides for the replacement/major repair of roofs and entrance canopies on buildings at all three campuses, including the addition of roof insulation as part of the replacement work. Project costs are based on comprehensive roof surveys of all College buildings completed in 2008. An update to this survey was completed in FY18.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$22.26M Total
Expenditures/Funding
$8.49M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Increase in FY26 due to additional projects in schedule. Remaining increase due to addition of FY27 and FY28. $1.4 million transferred to this project from Site Improvements project in FY22.

anchor

Justification

The College has implemented a roof replacement/renovation program to respond to the aging of building roofs. The program provides for the periodic evaluation of roofs on a four year cycle. The current roof replacement/major repair schedule delineates specific building projects.. Roofs requiring major renovation are generally ten years or older in age. In the initial replacement cycle, approximately 33% of the construction cost is for the addition of roof insulation on each building. Added insulation results in an average five year payback due to reduced energy costs and lower replacement costs of mechanical equipment retrofits in building renovations. This project is coordinated with the College's building renovation program and with the replacement of major roof-top building equipment. Related studies include the Montgomery College 2020 Strategic Plan, Collegewide Roof Surveys Update (2018), a Collegewide Facilities Condition Assessment Update (12/13) and the Collegewide Master Plan 2013-2023 (2/21).
anchor

Other

FY23 Appropriation: $500,000 (G.O. Bonds). FY24 Appropriation: $2,662,000 (G.O. Bonds). By County Council Resolution #12-663, the cumulative project appropriation was reduced by $65,000 in FY92. In addition, the State share was reduced by $65,000 in FY92. FY87-FY91, and FY93 project funding was 100% current revenue. FY92 funding was current revenue and State aid. No appropriations were made to this project in FY94 and FY95. In FY96, funding was changed to G.O Bonds and State aid. State aid applies only to roof replacement design and construction. Roof surveys are 100% County G.O. Bond funded. In FY19, $813,000 in G.O. Bonds was reallocated from the Bioscience Education Center project (#P056603) and $937,000 in G.O. Bonds were reallocated from the Science West Building Renovation project (#P076622). In FY19, $813,000 in G.O. Bonds reallocated from the Germantown Bioscience Education Center project (#P056603) and $937,000 reallocated from Science West Building Renovation (#P076622). The following fund transfer has been made into this project: $1,400,000 from the Planned Asset Replacement project (#P926659)(BOT Res. #19-05-041,5/13/19); The following fund transfers have been made to this project: $1,400,000 from Site Improvements (#076601) (BOT Resol. #22-09-004, 9/20/21).
anchor

Disclosures

Expenditures will continue indefinitely. Montgomery College asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Energy Conservation (CIP No. P816611), Planned Lifecycle Asset Replacement: College (CIP No. P926659), FY22 - Takoma Park/Silver Spring Health Sciences Center, and Rockville Campus Center; FY23 - Germantown High Technology Building, FY24 - Rockville Gudelsky Building, and Rockville Humanities Building; FY25 - Short Term Roof Repairs, Semi Annual Roof Inspections, and Rockville Central Services Building; FY26 - Rockville Macklin Tower, and Rockville Counseling and Advising Building; FY27 - Takoma Park/Silver Spring Commons Building (partial), and FY28 - Takoma/Silver Spring Mathematics Pavilion, North Pavilion, Pavilions 1, 2, and 4.
Download & Explore
Budget Snapshot
$22.26M Total
Expenditures/Funding
$8.49M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP876664
Date Last Modified01/08/22
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision210710614466001001001001001001000
Land00000000000
Site Improvements and Utilities00000000000
Construction201539939231978954002562174097050017230
Other00000000000
Total Expenditures22260110002765849550026621840107060018230
FUNDING (000s)
Funding SourceTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Current Revenue: General12481248000000000
G.O. Bonds1980985492765849550026621840107060018230
State Aid12031203000000000
Total Funding Sources22260110002765849550026621840107060018230
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request500
Year First AppropriationFY87
Appropriation FY 24 Request2662
Last FY's Cost Estimate18331
Cumulative Appropriation13765
Expenditure / Encumbrances11478
Unencumbered Balance2287