up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement/major repair of roofs and entrance canopies on buildings at all three campuses, including the addition of roof insulation as part of the replacement work. Project costs are based on comprehensive roof surveys of all College buildings completed in 2008. An update to this survey was completed in FY18.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$28.66M Total
Expenditures/Funding
$11.73M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Increase due to addition of FY29 and FY30 as well as cost increases for planned work in FY26 - FY30.
anchor

Justification

The College has implemented a roof replacement/renovation program to respond to the aging of building roofs. The program provides for the periodic evaluation of roofs on a four year cycle. The current roof replacement/major repair schedule delineates specific building projects.. Roofs requiring major renovation are generally ten years or older in age. In the initial replacement cycle, approximately 33% of the construction cost is for the addition of roof insulation on each building. Added insulation results in an average five year payback due to reduced energy costs and lower replacement costs of mechanical equipment retrofits in building renovations. This project is coordinated with the College's building renovation program and with the replacement of major roof-top building equipment. Related studies include the Montgomery College Strategic Plan (7/23), Collegewide Roof Surveys Update (2018), a Collegewide Facilities Condition Assessment (1/23) and the Collegewide Master Plan (Pending 2023).
anchor

Other

FY25 Appropriation: $1,840,000 (G.O. Bonds). FY26 Appropriation: $1,563,000 (G.O. Bonds). By County Council Resolution #12-663, the cumulative project appropriation was reduced by $65,000 in FY92. In addition, the State share was reduced by $65,000 in FY92. FY87-FY91, and FY93 project funding was 100% current revenue. FY92 funding was current revenue and State aid. No appropriations were made to this project in FY94 and FY95. In FY96, funding was changed to G.O Bonds and State aid. State aid applies only to roof replacement design and construction. Roof surveys are 100% County G.O. Bond funded. In FY19, $813,000 in G.O. Bonds was reallocated from the Bioscience Education Center project (#P056603) and $937,000 in G.O. Bonds were reallocated from the Science West Building Renovation project (#P076622). In FY19, $813,000 in G.O. Bonds reallocated from the Germantown Bioscience Education Center project (#P056603) and $937,000 reallocated from Science West Building Renovation (#P076622). The following fund transfer has been made into this project: $1,400,000 from the Planned Asset Replacement project (#P926659)(BOT Res. #19-05-041,5/13/19); The following fund transfers have been made to this project: $1,400,000 from Site Improvements (#076601) (BOT Resol. #22-09-004, 9/20/21).
anchor

Disclosures

Expenditures will continue indefinitely. Montgomery College asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Energy Conservation (CIP No. P816611), Planned Lifecycle Asset Replacement: College (CIP No. P926659), FY24 - Germantown High Technology Building, FY25- R-Macklin Tower Building (Terrace only). FY26- TPSS Pavilion 1, Pavilion 2, Pavilion 4, Short Term Roof Repairs, Semi Annual Roof Inspections; FY27 - R-South Campus Instruction Building, and TPSS Commons Building; FY28 - R-Gudelsky Building, and R-Humanities Building; FY28 - Rockville Theatre Arts Building, Rockville Technical Center, Germantown Grounds Storage; and FY30 - Central Services Building & R-Performing Arts Center.
Budget Snapshot
$28.66M Total
Expenditures/Funding
$11.73M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP876664
Date Last Modified01/05/24
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision3107112857914001002002004002502500
Land00000000000
Site Improvements and Utilities00000000000
Construction25551125962624103311740136310002372186619900
Other00000000000
Total Expenditures28658137243203117311840156312002772211622400
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Current Revenue: General12481248000000000
G.O. Bonds26207112733203117311840156312002772211622400
State Aid12031203000000000
Total Funding Sources28658137243203117311840156312002772211622400
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request1840
Year First AppropriationFY87
Appropriation FY 26 Request1563
Last FY's Cost Estimate22260
Cumulative Appropriation16927
Expenditure / Encumbrances13905
Unencumbered Balance3022