This project provides for the design and construction of new and renovation and expansion of existing central heating and cooling plants on the College's three campuses as recommended in the College's campus utilities master plan (12/12, and 2/13). The plan for a campus central plant, and distribution systems was included in the campus facilities master plan update (6/18). The project includes installation of boilers and chillers with associated equipment, the provision of natural gas service, and the construction of a hot water and chilled water distribution piping system to new and existing campus buildings.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$12.24M Total
Expenditures/Funding
$9.26M 6 Year Total
Expenditures/Funding
anchor

Cost Change

The College received an additional $823,000 in State Aid to be used for heating and cooling expansion and renovation.
anchor

Justification

This project implements the recommendations of the campus utilities master plan (12/12, and 2/13) and campus facilities master plan update (6/18). The campus' existing heating and cooling equipment is typically 20-30 years old and beyond its useful economic life. Due to the age of the equipment and increasing maintenance problems and costs, each campus is experiencing a significant increase in mechanical system problems and heating/cooling outages. Based on a life cycle cost analysis, the installation of a central heating/cooling plant offers significant equipment replacement, energy and maintenance savings to the College.
Collegewide Utilities Master Plan (Pending 2021), Montgomery College 2025 Strategic Plan, Collegewide Facilities Master Plan Update (6/18), VFA Facilities Condition Assessment (12/13).
anchor

Other

FY23 Appropriation: $1,937,000; ($1,000,000 (G.O. Bonds) and $937,000 (State Aid)). FY24 Appropriation: $2,323,000; ($1,000,000 (G.O. Bonds), and $1,323,000 (State Aid)). The need to provide new systems for heating and cooling campus buildings was articulated in the utilities master plan and satisfying this requirement is critical to new building construction and the planned renovation of the existing campus buildings.
anchor

Disclosures

Montgomery College asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Download & Explore
Budget Snapshot
$12.24M Total
Expenditures/Funding
$9.26M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP662001
Date Last Modified05/18/23
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision1000216847001002001001001001000
Land00000000000
Site Improvements and Utilities00000000000
Construction1123514541221856018372123900140090014000
Other00000000000
Total Expenditures122351670130592601937232310001500100015000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds8000695130560001000100010001000100010000
State Aid4235975032609371323050005000
Total Funding Sources122351670130592601937232310001500100015000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request1937
Year First AppropriationFY20
Appropriation FY 24 Request2323
Last FY's Cost Estimate11412
Cumulative Appropriation4912
Expenditure / Encumbrances1685
Unencumbered Balance3227