Early childhood programs in MCPS are targeted to children and families affected by poverty, including children with disabilities, and provides them with additional time to acquire literacy, mathematics, and social/emotional skills for success in school and later learning in life. These programs provide opportunities for children to build school-readiness skills by increasing social interactions, building oral language skills, and fostering vocabulary development. In MCPS, 65 elementary schools have locally funded Prekindergarten and/or federally funded Head Start classes. MCPS has two regional early childhood centers, one at the MacDonald Knolls Early Childhood Center in Silver Spring, serving 100 Prekindergarten students and the other at the Up-county Early Childhood Center, temporary housed at the Emory Grove Center in Gaithersburg, serving 80 Prekindergarten students. The Up-county center will be relocated in January 2022, and temporary housed at Watkins Mill High School utilizing existing classrooms within the building. This project will provide funding for MCPS to construct a stand alone building on the Watkins Mill High School site for the Up-county center, as well as begin planning to further expand early childhood centers throughout the county. An FY 2023 appropriation is requested for planning funds.
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$16M Total
Expenditures/Funding
$16M 6 Year Total
Expenditures/Funding
Budget Snapshot
$16M Total
Expenditures/Funding
$16M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP652303
Date Last Modified05/02/22
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision260000260085011106400000
Land00000000000
Site Improvements and Utilities122500122550072500000
Construction1182500118252650381553600000
Other35000350035000000
Total Expenditures1600000160004000600060000000
FUNDING (000s)
Funding SourceTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds1600000160004000600060000000
Total Funding Sources1600000160004000600060000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request4000
Year First Appropriation
Appropriation FY 24 Request12000
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0