up
Budget Year / Version:  
anchor
anchor
anchor

Description

Based on previous KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP included funding for a Major Capital Project at this school. It is anticipated that this Major Capital Project will include a significant addition that both addresses programmatic requirements, as well as increases capacity. Due to fiscal constraints, the County Council, in the adopted FY2021-2026 CIP approved the completion date for this project one year beyond the Board of Education's request. An FY 2023 appropriation was approved for the architectural planning and design for this project. An FY 2024 appropriation was approved for construction funds. As part of the Board of Education's Requested FY2025-2030 CIP, the construction timeline for this project was extended one-year. Therefore, this Major Capital Project was scheduled to be completed August 2027. However, due to fiscal constraints, as part of the County Council's approved FY2025-2030 CIP, construction expenditures were shifted to the outyears of the CIP with a "to be determined" completion date.

Beginning in 2025, MCPS hired a third party contractor to conduct facility assessments which led to a data set known as a Facility Condition Index (FCI). Along with the FCI, other relevant data sets were incorporated into a new CIP prioritization framework that led to the requested FY 2027 Major Capital Projects. Damascus HS was the highest-ranked high school candidate for a Major Capital Project. In the adopted FY2027-2032 CIP, the County Council approved the Board's request for planning to begin in FY 2027 with an expected completion date of August 2031.

project image
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the IAC Capital Improvement Program or the Built To Learn Act for school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP652114
Date Last Modified05/16/26
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaDamascus and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request9237
Year First AppropriationFY23
Appropriation FY28 Request268072
Last FY's Cost Estimate201869
Cumulative Appropriation21309
Expenditure / Encumbrances0
Unencumbered Balance21309