Description

A major effort as part of the CIP process has been to review the revitalization/expansion program to develop a multi-variable approach to determine the relative priority of large-scale renovations, possibly including programmatic and capacity considerations. As an evaluation of the previous process is reviewed and factors that could be used in a new process are considered, it is evident that the need for flexibility with respect to these major capital projects is imperative, as is the need to include instructional program priorities and the impact of overutilization. This new approach will eliminate the static and lengthy project queue that has been in place for many years.
In order to consider this new approach, the Board of Education must conduct a formal review process with respect to the two primary policies that guide the long-range educational facility planning framework. This review will allow for community engagement through formal public comments on the two policies. Therefore, at this point, the Board of Education, as part of the FY 2019-2024 CIP, has included funds in this project intended to create fiscal capacity in the CIP for these major capital projects and it is anticipated that future projects will be programmed using the expenditures shown in this project through the revised analysis and capital planning processes, once the Board of Education has completed its policy work.
As part of the amended FY 2019-2024 CIP, the Board of Education identified the following schools to begin the planning process as part of the Major Capital Projects: Burnt Mills, South Lake, Stonegate, and Woodlin elementary schools; Neelsville Middle School; and Damascus, Col. Zadok Magruder, Poolesville, and Thomas S. Wootton high schools.
During the County Council's review of the Board of Education's requested FY 2019-2024 amended CIP, due to fiscal constraints, some expenditures for this project were shifted into the outyears of the CIP. An FY 2020 appropriation was approved to begin planning for the schools identified above. Supplement B of the Superintendent's Recommended FY 2020 Capital Budget and Amended FY2019-2024 CIP provides additional detail for this project.
anchor

Phase

Planning Stage

Status

Closeout
anchor
Budget Snapshot
$0M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Mandatory Referral - M-NCPPC, Department of Environmental Protection, Building Permits:, Code Review, Fire Marshall, Department of Transportation, Inspections, Sediment Control, Stormwater Management, WSSC Permits
Download & Explore
Budget Snapshot
$0M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP651913
Date Last Modified01/06/20
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures00000000000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds00000000000
Total Funding Sources00000000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY20
Appropriation FY 22 Request0
Last FY's Cost Estimate119969
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0