Budget Year / Version:  
anchor
anchor
anchor

Description

High schools in the mid-county region will continue to be over capacity through the six-year planning period. Therefore, the Board of Education's requested FY 2019-2024 CIP included funding for a new high school in the mid-county region located on the Crown site in the City of Gaithersburg. An FY 2019 appropriation was requested to begin planning this new high school. Due to fiscal constraints, the County Council approved a one-year delay for this project. During the County Council's review of the FY 2019-2024 Amended CIP, the Council approved including the following language in this project to keep two clusters from going into housing moratoria in FY 2020: "Based on the Board of Education's proposed yearly spending in this project, the Council anticipates that Crown HS will open in September 2024. The new school will relieve overcrowding by at least 150 students at Quince Orchard HS and by at least 120 students at Richard Montgomery HS." An FY 2020 appropriation was approved for planning funds. Due to fiscal constraints, the County Council, in the adopted FY2021-2026 CIP delayed this project one year. This new high school is scheduled to be completed September 2026.
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$136.3M Total
Expenditures/Funding
$99.78M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Coordination

Mandatory Referral - M-NCPPC, Department of Environmental Protection, Building Permits:, Code Review, Fire Marshall, Department of Transportation, Inspections, Sediment Control, Stormwater Management, WSSC Permits
Download & Explore
Budget Snapshot
$136.3M Total
Expenditures/Funding
$99.78M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP651909
Date Last Modified11/17/20
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaGaithersburg and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision630601522478418911761500632000
Land00000000000
Site Improvements and Utilities150160015016024054395602373500
Construction11068000756800006011273594231035000
Other43000043000000315011500
Total Expenditures136302015229978018912001593912245342444346035000
FUNDING (000s)
Funding SourceTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds136302015229978018912001593912245342444346035000
Total Funding Sources136302015229978018912001593912245342444346035000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY20
Appropriation FY 22 Request0
Last FY's Cost Estimate136302
Cumulative Appropriation6306
Expenditure / Encumbrances0
Unencumbered Balance6306