Description

This ongoing project provides studies for bridge projects under consideration for inclusion in the Capital Improvements Program (CIP). Bridge Design serves as a transition stage for a project between identification of need and its inclusion as a stand-alone construction project in the CIP. Prior to the establishment of a stand-alone project, the Department of Transportation will complete a design which outlines the general and specific features required on the project. Selected projects range in type, but typically consist of upgrading deficient bridges so that they can safely carry all legal loads which must be accommodated while providing a minimum of two travel lanes. Candidate projects currently included are listed in the Other section below.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$43.9M Total
Expenditures/Funding
$12.6M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase due to the addition of funds to complete design of four bridges within the six-year period and the addition of FY31 and FY32 to this ongoing level-of-effort project.
anchor

Justification

There is continuing need for the development of accurate cost estimates and an exploration of alternatives for proposed projects. Bridge Design costs for all projects which ultimately become stand-alone CIP projects are included here. These costs will not be reflected in the resulting individual project. Future individual CIP projects, which result from Bridge Design, will each benefit from reduced planning and design costs. Biennial inspections performed since 1987 have consistently shown that the bridges currently included in the project for design studies are in need of major rehabilitation or replacement.
anchor

Other

Candidates for this program are identified through the County Biennial Bridge Inspection Program as being deficient, load restricted, or geometrically substandard. The Planning, Design, and Supervision (PD&S) costs for all bridge designs include all costs up to contract preparation. At that point, future costs and Federal aid will be included in stand-alone projects. Candidate Projects: Brink Rd Bridge #M-0064, Glen Rd Bridge #M-0015, Mouth of Monocacy Rd Bridge #M-0043, Zion Rd Bridge #M-0121, Schaeffer Rd Bridge #M-0137, Parklawn Entr Bridge #MPK-17, Baltimore Rd Bridge #M-0201, Brighton Dam Rd Bridge #M-0108, Brookeville Rd Bridge #M-0083, Greentree Rd Bridge #M-0180, Whites Ferry Rd Bridge #M-0186, Glen Rd Bridge #M-0013, Barnes Rd Bridge #M-0008, Barnesville Rd Bridge #M-0045, Randolph Rd Bridge #M-0080-3, Shady Grove Rd Bridge #M-0191-3, Beach Dr Bridge #MPK-05, Beach Dr Bridge #MPK-08, Bel Pre Rd Bridge #M-0092, Little Falls Pkwy Bridge #MPK-01-2, Cattail Rd Bridge #M-0155, Harris Rd Bridge #M-0046, Valleywood Dr Bridge #M-0254, Hawkins Landing Dr Bridge #M-0317, Kensington Parkway Bridge #M-0073, Midcounty Hwy Bridge #M-0219, Southlawn Rd Bridge #M-0050, Martinsburg Rd Bridge #M-0042, Burnt Hill Rd Bridge #M-0157, Wynnfield Dr Bridge #M-0529, Wynnfield Dr Bridge #M-0530, and Quince Orchard Rd Bridge #M-0023.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. Expenditures will continue indefinitely. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Federal Highway Administration - Federal Aid Bridge Replacement and Rehabilitation Program, Maryland State Highway Administration, Maryland Department of the Environment, Maryland Department of Natural Resources, Maryland Historic Trust, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Utilities, U.S. Army Corps of Engineers, CSX Transportation, Washington Metropolitan Area Transit Authority, and Rural Rustic Roads Legislation
Budget Snapshot
$43.9M Total
Expenditures/Funding
$12.6M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP509132
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision43073248775596126002100210021002100210021000
Land549549000000000
Site Improvements and Utilities107107000000000
Construction154154000000000
Other1818000000000
Total Expenditures43901257055596126002100210021002100210021000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid956956000000000
G.O. Bonds40446223255521126002100210021002100210021000
Land Sale1515000000000
PAYGO340340000000000
Recordation Tax Premium (MCG)7507500000000
State Aid20692069000000000
Total Funding Sources43901257055596126002100210021002100210021000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request4200
Year First AppropriationFY91
Appropriation FY 28 Request0
Last FY's Cost Estimate39207
Cumulative Appropriation31301
Expenditure / Encumbrances28637
Unencumbered Balance2664