Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the installation and improvement of capital amenities at bus stops in Montgomery County to make them safer, more accessible and attractive to users, and improve pedestrian safety for County transit passengers. These enhancements can include items such as sidewalk connections, improved pedestrian access, pedestrian refuge islands and other crossing safety measures, area lighting, paved passenger standing areas, and other safety upgrades. In prior years, this project included funding for the installation and replacement of bus shelters and benches along Ride On and County Metrobus routes. Benches and shelters are now handled under the operating budget. Full-scale construction began in October 2006. Through FY21, approximately 3,618 stops with 1,333 curb ramps; 422 concrete kneewalls for safety and seating; 89,957 linear feet of sidewalk; and 179,531 linear feet of ADA concrete pads have been modified or installed.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$7.92M Total
Expenditures/Funding
$2.4M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase due to addition of FY27-FY28 to this ongoing level of effort project.
anchor

Justification

Many of the County's bus stops have safety, security, or right-of-way deficiencies since they are located on roads which were not originally built to accommodate pedestrians. Problems include: lack of drainage around the site, sidewalk connections, passenger standing areas or pads, lighting or pedestrian access, and unsafe street crossings to get to the bus stop. This project addresses significant bus stop safety issues to ease access to transit service. Correction of these deficiencies will result in fewer pedestrian accidents related to bus riders, improved accessibility of the system, increased attractiveness of transit as a means of transportation, and greater ridership. Making transit a more viable option than the automobile requires enhanced facilities as well as increased frequency and level of service. Getting riders to the bus and providing an adequate and safe facility to wait for the bus will help to achieve this goal. The County has approximately 5,400 bus stops. The completed inventory and assessment of each bus stop has determined what is needed at each location to render the stop safe and accessible to all transit passengers. In FY05, a contractor developed a GIS-referenced bus stop inventory and condition assessment for all bus stops in the County, criteria to determine which bus stops need improvements, and a prioritized listing of bus stop relocations, improvements, and passenger amenities. The survey and review of bus stop data have been completed and work is on-going.
anchor

Other

Expenditures will continue indefinitely.
anchor

Fiscal Note

Funding for this project includes general obligation bonds with debt service financed from the Mass Transit Facilities Fund.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Civic Associations, Municipalities, Maryland State Highway Administration, Maryland Transit Administration, Washington Metropolitan Area Transit Authority, Commission on Aging, Commission on People with Disabilities, Montgomery County Pedestrian Safety Advisory Committee, Citizen Advisory Boards
Download & Explore
Budget Snapshot
$7.92M Total
Expenditures/Funding
$2.4M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP507658
Date Last Modified10/05/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision426230942089601601601601601601600
Land73756916800000000
Site Improvements and Utilities00000000000
Construction270942584414402402402402402402400
Other208208000000000
Total Expenditures79164296122024004004004004004004000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Current Revenue: Mass Transit47181098122024004004004004004004000
G.O. Bonds31983198000000000
Total Funding Sources79164296122024004004004004004004000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request400
Year First AppropriationFY76
Appropriation FY 24 Request400
Last FY's Cost Estimate7916
Cumulative Appropriation5916
Expenditure / Encumbrances4651
Unencumbered Balance1265