Description

This program provides for the planning, design, and construction of bikeways, trails, neighborhood greenways and directional route signs throughout the County to develop the bikeway network specified by master plans and those requested by the community to provide access to commuter rail, mass transit, major employment centers, recreational and educational facilities, and other major attractions. The program will construct bicycle facilities that typically cost less than $1.0 million including shared use paths, on-road bicycle facilities, wayfinding, and signed shared routes.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$33.3M Total
Expenditures/Funding
$13.11M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase is due to minor annual funding adjustments and the addition of FY31 and FY32 to this level of effort project.
anchor

Justification

There is a continuing and increasing need to develop a viable and effective bikeway and trail network throughout the County to increase bicyclist safety and mobility, provide an alternative to the use of automobiles, reduce traffic congestion, reduce air pollution, conserve energy, enhance quality of life, provide recreational opportunities, and encourage healthy lifestyles. This program implements the bikeways recommended in local area master plans, in the November 2018 Approved and Adopted Montgomery County Bicycle Master Plan, and those identified by individuals, communities, the Montgomery County Bicycle Action Group, and bikeway segments and connectors necessitated by the subdivision process. Projects identified by individuals and communities will be used as an ongoing project guide which will be implemented in accordance with the funds available in each fiscal year. This program also complements and augments the bikeways that are included in road projects and supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities to zero on all roads by 2030.
anchor

Other

Recently completed projects include Emory Lane shared-use path, Muncaster Mill Road shared-use path, and Marinelli Road separated bike lanes. Ongoing projects include Heritage Triangle Trail, Norwood Road shared use path, and Washington Grove - Brown Street connector path. Projects included within the 6-year CIP are Executive Blvd/Grand Park Ave separated bike lanes, Glen Echo-CCT connector trail, Layhill Road shared-use path, Good Hope Road shared-use path extension, Friendship Blvd bikeway, and Broadbirch Drive separated bike lanes.
anchor

Fiscal Note

$814,000 in developer contributions programmed in FY26 and FY27 to complete design and permitting from the Bullis School entrance to Democracy Boulevard as well as construct improvements along Falls Road. FY25 actuals funding switch between GO Bonds, Impact Taxes and Contributions.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. Expenditures will continue indefinitely. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland Department of Transportation State Highway Administration, Maryland-National Capital Park and Planning Commission, Department of Police, Citizen Advisory Boards, Montgomery County Bicycle Action Group, Coalition for the Capital Crescent Trail, Montgomery Bicycle Advocates, Washington Area Bicyclist Association, Washington Metropolitan Area Transit Authority, Department of Permitting Services, Bullis School, and Utility Companies.
Budget Snapshot
$33.3M Total
Expenditures/Funding
$13.11M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP507596
Date Last Modified01/11/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision140997616113653473501108113812936637950
Land59731879200000020000
Site Improvements and Utilities89057231800000000
Construction177183893625875672264992962807123713050
Other00000000000
Total Expenditures33304123997791131142614210021002100210021000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Contributions10361036000000000
G.O. Bonds2312832657263126002100210021002100210021000
Impact Tax65626562000000000
State Aid25781536528514514000000
Total Funding Sources33304123997791131142614210021002100210021000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance30345666
Energy30345666
NET IMPACT606810121212
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request2614
Year First AppropriationFY75
Appropriation FY 28 Request2100
Last FY's Cost Estimate28822
Cumulative Appropriation20190
Expenditure / Encumbrances15377
Unencumbered Balance4813