up
Budget Year / Version:  
anchor
anchor
anchor

Description

The total project is comprised of 3 phases. Phase I includes a 4,200 foot segment of Oak Drive and a 350 foot segment of Kingstead road. This phase provides a 5' concrete sidewalk with green buffer along the west side of Oak Drive from its southern intersection with MD 27 to the John T. Baker Middle School. A 5' sidewalk is also provided along the south side of Kingstead Road from Oak Drive to the John Haines park. Phase II will include a 2,300 foot segment of MD 27 (Ridge Road) starting at the northern intersection with Oak Drive and ending at the existing sidewalk at Damascus High School. Phase III will include a 2,500 foot segment of MD 27 (Ridge Road) starting at the southern intersection with Oak Drive and ending at the existing sidewalk at Ridge Landing Place.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$12.51M Total
Expenditures/Funding
$11.1M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Phase I started in FY19 and will be complete in FY21. Phases II and III Final Design will start in FY25. The implementation schedule is based on an estimate of 6 months to complete Phase 2, followed by 12 months to complete Phase 3
anchor

Justification

The project is needed to address the lack of continuous and safe pedestrian access to existing sidewalks and bikeways, transit stops, commercial areas, and community and public facilities in the Damascus area. The 2006 Damascus master plan and 2018 Countywide Bikeways Master Plan recommends sidewalk in the project area.
anchor

Other

The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030.
anchor

Fiscal Note

Construction cost estimates for Phase II and Phase III will be updated during the final design.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Department of Permitting Services, Department of Environmental Protection, State Highway Administration, Maryland-National Capital Park and Planning Commission, PEPCO, Washington Gas, Washington Suburban Sanitation Commission, Verizon
Budget Snapshot
$12.51M Total
Expenditures/Funding
$11.1M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501908
Date Last Modified04/14/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaDamascus and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision3240993631050014591435142690
Land26164422791895000012656300
Site Improvements and Utilities15800231557000011004570
Construction5075053745380000248820500
Other00000000000
Total Expenditures12511541875110950014591435499532060
FUNDING (000s)
Funding SourceTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds12511541875110950014591435499532060
Total Funding Sources12511541875110950014591435499532060
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request0
Year First AppropriationFY19
Appropriation FY 24 Request0
Last FY's Cost Estimate12511
Cumulative Appropriation1416
Expenditure / Encumbrances918
Unencumbered Balance498