The purpose of this project is to replace vital transit technology systems, enhance system accountability, and maintain electronic information signs throughout the county. This is part of the Division of Transit Services IT plan to maintain and expand our intelligent transit systems for compatibility, accountability, and safety.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$18.07M Total
Expenditures/Funding
$3M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Replacement of the Computer Aided Dispatch/Automatic Vehicle Locator (CAD/AVL) system in FY19-23; maintenance and upgrades of Real Time informational signs and other systems in FY23-28.
anchor

Cost Change

Cost increase due to addition of FY27-FY28 to this ongoing level of effort project, partially offset by FY25 and FY26 reductions to maintain annual funding at $500,000.
anchor

Justification

The CAD/AVL system has reached the end of its useful life, and the system is experiencing critical operational issues such as gaps when no information is available to dispatch and on field operations. The upgrade from radio to cellular technology will eliminate dead zones and allow vehicle locations to be updated every 10 seconds rather than the current three minutes. The CAD/AVL is a crucial driver to continue with the Real Time sign program both in LED Ride On/WMATA stop signs and multimodal signs in buildings around the county.
anchor

Disclosures

Expenditures will continue indefinitely. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Department of Technology and Enterprise Business Solutions, Washington Metropolitan Area Transit Authority, and regional local transit operators.
Budget Snapshot
$18.07M Total
Expenditures/Funding
$3M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP501801
Date Last Modified01/11/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities180727454761830005005005005005005000
Construction00000000000
Other00000000000
Total Expenditures180727454761830005005005005005005000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Current Revenue: Mass Transit55001007149330005005005005005005000
Short-Term Financing121006196590400000000
State Aid47225122100000000
Total Funding Sources180727454761830005005005005005005000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request500
Year First AppropriationFY18
Appropriation FY 24 Request500
Last FY's Cost Estimate18072
Cumulative Appropriation15572
Expenditure / Encumbrances13094
Unencumbered Balance2478