Description

This program will provide for the replacement of failed storm drain pipes and culverts. The County's storm drain infrastructure is aging and many of the metal pipe culverts installed from 1960 through the 1990's have reached the end of their service life. An asset inventory with condition assessments has been developed to better forecast future replacement needs. Going forward, funding will be programmed for both systematic and emergency replacement of these pipes and culverts. Program scope includes: storm water pipe and culvert replacement of both metal and concrete less than six (6) feet in roadway longitudinal length; headwalls, end sections, replacement, or extension of culverts to assure positive flow of stormwater and channeling of stormwater into existing ditch lines or structures. Repairs also include roadside pipe and culvert end treatment safety improvements to eliminate safety hazards. This project will not make major changes to the location or size of existing storm drainage facilities. Structures greater than six-feet-roadway-longitudinal length are repaired under the Bridge Renovation Program, (CIP No. 509753).
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$26.7M Total
Expenditures/Funding
$13.5M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Scope increase in FY23 includes four new subprojects for the following culverts, all of which have recently been discovered to be severely deteriorating: Crabbs Branch storm drain, Wightman Road culvert, Centerway Road culvert, and Tucker Lane culvert. Funding for FY27 and FY28 has also been added to this level of effort project.
anchor

Justification

This program will address emergency pipe replacements of aging metal and concrete pipes that have reached the end-of-their-service life. The result of these pipe failures has been deep depressions, sinkholes, sediment build-up, open pipe joints, and metal pipe inverts to an unacceptable levels. Existing storm drain conditions are extremely poor. Repairs are needed to improve safety and reduce the potential for hazards and associated public inconvenience. Failure of a storm drain pipe will precipitate emergency repairs at much higher prices. Furthermore, this program provided funding towards developing an asset inventory of the storm drain system including pipe and culvert conditions that helps forecast future funding requirements.
anchor

Fiscal Note

In FY23-FY28, long-term financing based on the Maryland Water Quality Revolving Loan Fund (WQRLF) was replaced with Water Quality Protection Bonds due to limited eligibility of projects within this CIP under the revolving fund. FY22 amendment to reduce Long-Term Financing and replace it with Water Quality Protection Bonds. FY23 funding switch between WQPC Bonds and Current Revenue from the WQPC fund.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Washington Suburban Sanitary Commission, Washington Gas Company, Montgomery County Department of Permitting Services, Pepco, Cable TV, Verizon, Montgomery County Public Schools, Regional Service Centers, Community Association's, Commission on People With Disabilities, Maryland Department of Environment, Montgomery County Department of Environmental Protection, and United States Army Corps of Engineers.
Download & Explore
Budget Snapshot
$26.7M Total
Expenditures/Funding
$13.5M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP501470
Date Last Modified03/30/22
Administering AgencyTransportation
CategoryConservation of Natural Resources
SubCategoryStorm Drains
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision3596130346318305552552552552552550
Land00000000000
Site Improvements and Utilities00000000000
Construction23102101551277116704445144514451445144514450
Other22000000000
Total Expenditures26700114601740135005000170017001700170017000
FUNDING (000s)
Funding SourceTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Current Revenue: Water Quality Protection90004000050005000000000
G.O. Bonds15001500000000000
Long-Term Financing360035604000000000
Water Quality Protection Bonds126002400170085000170017001700170017000
Total Funding Sources26700114601740135005000170017001700170017000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request5000
Year First AppropriationFY14
Appropriation FY 24 Request1700
Last FY's Cost Estimate20000
Cumulative Appropriation13200
Expenditure / Encumbrances11476
Unencumbered Balance1724