up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the funding of the Capital Crescent trail, including the main trail from Woodmont Avenue in Bethesda to Silver Spring as a largely 12-foot-wide hard surface hiker-biker path, connector paths at several locations, a new bridge over Connecticut Avenue, a new underpass beneath Jones Mill Road, a new tunnel beneath Wisconsin Avenue, Phase 2 of the Capital Crescent Surface Trail Project along 47th Street which was previously included in CIP No. 500119, supplemental landscaping and amenities, and lighting at trail junctions, underpasses, and other critical locations.
project image
anchor

Phase

Under Construction

Status

Active
anchor
Budget Snapshot
$130.66M Total
Expenditures/Funding
$81.3M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Construction of the tunnel under Wisconsin to start FY25 and be completed in FY27.
anchor

Cost Change

Increased PDS costs due to delayed Purple Line construction schedule by MTA and life/safety design for tunnel. Additionally, increased PDS, SIU and Construction costs due to escalation/inflation of the FY20 cost estimates for the CCT Tunnel.
anchor

Justification

This trail will be part of a larger system to enable non-motorized traffic in the Washington, DC region. This trail will connect to the existing Capital Crescent Trail from Bethesda to Georgetown, the Metropolitan Branch Trail from Silver Spring to Union Station, and the Rock Creek Bike Trail from northern Montgomery County to Georgetown. The trail will serve pedestrians, bicyclists, joggers, and skaters, and will be compliant with the Americans with Disabilities Act of 1990 (ADA), the Bethesda CBD Sector Plan, and the Purple Line Functional Master Plan. The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County roadways to zero.
anchor

Fiscal Note

In March of 2021, the schedule was adjusted to shift funding from each year to the next year from FY21 through FY25 to further reflect the expected construction progress and estimated billing schedule based on the Purple Line's plan to re-solicit a new general contractor to complete the project. Previously, tunnel costs were based on estimates developed in FY20. In FY21 and FY22, construction markets experienced approximately 10% escalation annually. Historically, escalation has been at 3% annually. The County has applied to the federal government for a Rebuilding American Infrastructure for Sustainability and Equity (RAISE) grant of $45 million, which requires a non-federal match of $24 million. If this grant is not secured, the schedule for the tunnel will be reevaluated.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland Transit Administration, Maryland Department of Transportation, State Highway Administration, Maryland-National Capital Park and Planning Commission, Bethesda Bikeway and Pedestrian Facilities, Coalition for the Capital Crescent Trail, CSX Transportation, Washington Metropolitan Area Transit Authority. Special Capital Projects Legislation [Bill No. 32-14] was adopted by Council by June 17, 2014.
Budget Snapshot
$130.66M Total
Expenditures/Funding
$81.3M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501316
Date Last Modified05/12/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision13081314875391804021018903520352000
Land11901190000000000
Site Improvements and Utilities290880290001005001300100000
Construction1104833372110541662214813400811400230002300000
Other30000030003000000000
Total Expenditures1306623806711294813017853431813790278202752000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Federal Aid450000045000009029180831788800
G.O. Bonds57196169239688305852137431847619737963200
Impact Tax2729221144160645424542000000
Recordation Tax Premium (MCG)11740011741174000000
State Aid00000000000
Total Funding Sources1306623806711294813017853431813790278202752000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request323
Year First AppropriationFY15
Appropriation FY 24 Request4448
Last FY's Cost Estimate116097
Cumulative Appropriation57214
Expenditure / Encumbrances39720
Unencumbered Balance17494