Description

This project develops and implements plans for the prevention of pollution and the abatement and containment of potential pollution sources at County facilities - including the Department of Transportation, the Department of General Services depots and maintenance shops, and other county facilities and offices. This project provides for the design and construction of structural covered areas to ensure appropriate storage of hazardous materials and potential pollution sources at County depots. Work will also include replacement of the salt barns at County depots and addressing environmental compliance issues of petroleum Underground Storage Tanks (USTs) and associated piping at County facilities. This program also addresses environmental concerns such as indoor air quality issues, mold, radon, lead paint and lead in drinking water.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$24.5M Total
Expenditures/Funding
$8.4M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

FY21: Colesville Depot Fueling Station, Council Office Building (COB) Fueling Station.
FY22: Fueling Station at 5th District Police Station, Damascus Depot Fueling Station.
anchor

Cost Change

Addition of FY25 and FY26 to this level-of-effort project.
anchor

Justification

This project is supported by the Pollution Prevention Plan (P2) for County facilities and the Storm Water Pollution Prevention Plans (SWPPP) for County facilities to comply with aspects of the Federal Clean Water Act National Pollutant Discharge Elimination System (NPDES) Notice of Intent (NOI). Each of the County maintenance facilities must implement appropriate pollution prevention techniques to reduce contamination of stormwater runoff. Covered areas are required under the NPDES for all hazardous products and liquid drums that are stored outside to avoid the potential of drum deterioration, leakage, and/or runoff contamination. Structural improvements of covered areas and salt barn structures are scheduled at the Silver Spring, Poolesville, and Bethesda Depots. This project also includes efforts to address environmental compliance issues of UST's and associated piping at County facilities.
anchor

Fiscal Note

In FY18, $140,000 was transfered to Planned Lifecycle Asset Replacement for the Data Center UPS system.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Department of General Services, Department of Transportation, Department of Permitting Services, Department of Environmental Protection, and Maryland Department of the Environment.
Download & Explore
Budget Snapshot
$24.5M Total
Expenditures/Funding
$8.4M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP500918
Date Last Modified01/09/20
Administering AgencyGeneral Services
CategoryGeneral Government
SubCategoryCounty Offices and Other Improvements
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision4484258240215002502502502502502500
Land00000000000
Site Improvements and Utilities681681000000000
Construction161797311196869001150115011501150115011500
Other31593159000000000
Total Expenditures2450313733237084001400140014001400140014000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Contributions00000000000
Current Revenue: Water Quality Protection130013000000000
G.O. Bonds2437313733224084001400140014001400140014000
Total Funding Sources2450313733237084001400140014001400140014000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request1400
Year First AppropriationFY09
Appropriation FY 22 Request1400
Last FY's Cost Estimate21703
Cumulative Appropriation16103
Expenditure / Encumbrances14525
Unencumbered Balance1578