This project provides repairs and renovations to parking lots at transit park and ride lots and transit centers to allow them to continue functioning as transit facilities and comply with Americans with Disabilities Act (ADA) requirements. In FY08/FY09, an evaluation and assessment of all park and ride facilities, including ADA accessibility and pedestrian safety, was completed to provide scope and detailed cost estimates for the restoration and upgrades.
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$3.04M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

The plan calls for the following site renovations: FY17: Colesville Park and Ride, Greencastle Park and Ride FY18: Kingsview Park and Ride.
anchor

Justification

The County operates 8 transit park and ride lots and 3 transit centers in major transportation corridors. Several County park and ride lots have had major failures, resulting from the age and use of the facilities. Some of the lots were constructed more than 20 years ago. Pavement and the entrances were not constructed to support heavy bus traffic.
anchor

Other

Schedule was delayed to FY16 pending work with the Department Of Environmental Protection (DEP) on Low Impact Design (LID) to manage stormwater as close to its source as possible. At the park and ride lots DEP has designed and will manage the bio-rentention facilities, rain gardens and permeable pavements. Lots include: Greencastle and Colesville Park and Ride lots.
anchor

Fiscal Note

Funding for this project is general obligation bonds dedicated to Mass Transit with debt service financed from the Mass Transit Facilities Fund.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland State Highway Administration, Department of Permitting Services, Maryland-National Capital Park and Planning Commission, Utilities, Department of Environmental Protection
Download & Explore
Budget Snapshot
$3.04M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP500534
Date Last Modified11/03/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision331331000000000
Land00000000000
Site Improvements and Utilities55000000000
Construction1807112867900000000
Other896896000000000
Total Expenditures3039236067900000000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds3039236067900000000
Total Funding Sources3039236067900000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request0
Year First AppropriationFY05
Appropriation FY 24 Request0
Last FY's Cost Estimate3039
Cumulative Appropriation3039
Expenditure / Encumbrances2985
Unencumbered Balance54