anchor Description
With the construction of the new Multi-Agency Service Park and the relocation of the Public Safety Training Acadamy activities to that facility, this project provides for the redevelopment of the existing PSTA site. The project will involve the demolition and environmental clean up of the site, staff time to oversee those activities, the redevelopment of the site, the Corridor Cities Transitway, and proposed bikeways in the Shady Grove master plan area.
anchorEstimated Schedule
The existing uses were relocated in FY17. Demolition and environmental clean were completed in FY19. Anticipate completing sale of land to the Elms at PSTA, LLC in FY22.
anchorCost Change
Cost reduced to reflect savings following project completion.
anchor Justification
The redevelopment of the site is part of the County's Smart Growth Initiative.
anchorCoordination
Department of Police, Department of Correction and Rehabilitation, Montgomery County Fire and Rescue Service, Department of General Services, Multi-Agency Driver Training Facility, Office of Management and Budget, and M-NCPPC.