This level-of-effort project is needed to maintain the County's building infrastructure. This project funds the wholesale replacement of aged and outdated building envelope systems including the replacement of windows, exterior doors, siding, exterior walls, and weatherproofing. This project provides for a systematic replacement to maintain the building envelope, protect the building integrity, and allow for continued full and efficient use of County buildings.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$20.22M Total
Expenditures/Funding
$9.3M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Several projects will be completed during FY23 and FY24.

FY23 and FY24
Aspen Hill Library.
Montgomery County Correctional Facility Loading Dock.
401 Hungerford Drive.
Colesville Health Center.


Replace windows at 2 County Libraries
Replace three (3) front/back rolling doors at 3 County Fire Stations.
anchor

Cost Change

Cost increase is due to the addition of expenditures in FY27 and FY28 for this ongoing project.
anchor

Justification

Window replacements, siding replacements, and exterior door replacements are critical to protect the life of a facility. Windows and doors can eliminate drafts to improve both comfort and energy efficiency. Siding protects the facility by eliminating potential leaks that can lead to damage of other facility components as well as creating health issues such as mold growth.
anchor

Other

Building envelope repairs have been neglected for many years. Many facilities still have single and/or double pane glass windows and are poorly sealed, leading to energy loss. Many exterior metal doors are rusted and frequently fail to close and latch which creates a safety hazard. Renovations will address leaks around windows and doors and will provide improved energy efficiency.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Department of General Services and Departments affected by building envelope repair projects.
Budget Snapshot
$20.22M Total
Expenditures/Funding
$9.3M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP361501
Date Last Modified01/12/22
Administering AgencyGeneral Services
CategoryGeneral Government
SubCategoryCounty Offices and Other Improvements
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision3278128722117702952952952952952950
Land00000000000
Site Improvements and Utilities00000000000
Construction169376989241875301255125512551255125512550
Other00000000000
Total Expenditures202158276263993001550155015501550155015500
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds202158276263993001550155015501550155015500
Total Funding Sources202158276263993001550155015501550155015500
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request1550
Year First AppropriationFY15
Appropriation FY 24 Request1550
Last FY's Cost Estimate20215
Cumulative Appropriation12465
Expenditure / Encumbrances9295
Unencumbered Balance3170