up
Budget Year / Version:  
anchor
anchor
anchor

Description

This program provides for an on-going comprehensive effort to ensure that all parks and park facilities are built, renovated, and maintained in compliance with Title II of the Americans with Disabilities Act (ADA) and the 2010 ADA Standards for Accessible Design. This program includes both the correction of deficiencies identified by the United States Department of Justice (DOJ) during its Project Civic Access assessment of various park facilities, the results of a comprehensive self-evaluation process as well as efforts to comply with the revisions to Title II of the ADA, which went into effect on March 15, 2011. Improvements may include, but are not limited to, grading, pavements, site amenities, drainage improvements, building modifications, signage, etc. and are often combined with other projects.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$10.27M Total
Expenditures/Funding
$4.73M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Increase due to the addition of two fiscal years to this ongoing project.
anchor

Justification

Montgomery County was selected by the DOJ for a Project Civic Access (PCA) review in 2006. The PCA is a proactive, ongoing initiative of the Disability Rights Section of the DOJ Civil Rights Division to ensure ADA compliance in local and state governments throughout the country. Montgomery County and M-NCPPC entered into a Settlement Agreement with DOJ on August 16, 2011, that required the County and M-NCPPC to remediate specific issues identified by DOJ within a negotiated timeline, conduct a comprehensive self-evaluation, and develop a Transition Plan for barrier removal, including efforts to comply with the updated Title II requirements.. All self-evaluations were completed ahead of schedule and the Final Transition Plan submitted in August 2016 and subsequently accepted by DOJ. The Final Transition Plan provides a summary of all barriers found, a strategy and timeline for their removal, as well as planning level cost estimates. The Final Transition Plan identified approximately 13,600 barriers with a projected planning level cost estimate of $31 million for barrier removal system-wide, although actual costs are expected to be significantly higher based upon work completed to date.
anchor

Fiscal Note

Prior year partial capitalization of expenditures through FY16 totaled $1,934,000.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

United States Department of Justice, County Attorney's Office, Department of General Services, ADA Compliance: Non-Local Parks, PDF 128702
Download & Explore
Budget Snapshot
$10.27M Total
Expenditures/Funding
$4.73M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP128701
Date Last Modified10/24/22
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision13955942016001001001001001001000
Land00000000000
Site Improvements and Utilities88723546119641307807007006506506500
Construction00000000000
Other00000000000
Total Expenditures102674140139747308808008007507507500
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
M-NCPPC Bonds102674140139747308808008007507507500
Total Funding Sources102674140139747308808008007507507500
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request880
Year First AppropriationFY12
Appropriation FY 24 Request800
Last FY's Cost Estimate10267
Cumulative Appropriation6417
Expenditure / Encumbrances4426
Unencumbered Balance1991