Description

This project provides funding for WSSC's share of Blue Plains-associated projects which are outside the fence of the treatment plant. Major projects include: Potomac Interceptor Rehabilitation Upper Potomac interc Eptor; Potomac Sewage Pumping Station Rehabilitation; Influent Sewers Rehabilitation; and the new projects associated with the Combind Sewer Overflow (CSO) Long Term Control Plan (e.g. Anacostia Tunnel).
project image
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$225.9M Total
Expenditures/Funding
$187.08M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Justification

The Blue Plains Intermunicipal Agreement of 1985; the WASA camp that (1998); and the DC-WASA Approved FY 2008-FY 2017 Capital Improvement Program information (January 2009). Specific Date: This is a continuation of the DC-WASA's upgrading of the Blue Plains-associated projects outside the fence. Cost Change: The cost of this project has increased due to the addition of the Associated Tunnel portion of the Anacostia Tunnel portion of the Long Term Control Program.
anchor

Other

This project scope was developed for the FY 2011 CIP and has an estimated cost of $75,836.00. The project is split from the existing S-22.09, Blue Plains WWTP: Plant-wide Projects. The creation of this Pipeline & Appurtenances Project is justified by language in the Blue Plains Intermunicipal Agreement, and the expected increases in costs for new and existing projects outside the fence. Expenditure shown above include costs for currently active projects outside the fence which were previously shown in the Plant-wide project. Project costs are derived from the DC-WASA Capital & Operating Budget 10-year forecast in latest project PDF does not fully reflect the total project costs. These projects are, in fact expected to continue indefinitely. As new sub-projects added to the Blue Plains facility plans, the associated costs will be added to the project. The funding schedule also indicates the calculated Rockville share of the cost.
anchor

Coordination

District Of Columbia Water & Sewer Authority (responsible for design and construction). This project supports 45% System Improvements and 55% Environmental Regulation.
Budget Snapshot
$225.9M Total
Expenditures/Funding
$187.08M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP113804
Date Last Modified11/30/22
Administering AgencyW.S.S.C.
CategoryWSSC
SubCategorySewerage Bi-County
Planning AreaBi-County
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Est FY23Total 6 YearsFY 24FY 25FY 26FY 27FY 28FY 29Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction22366001357818522816289182633676451157408272192824854
Other223801361853163183368512408219249
Total Expenditures22589801371418708116452184463713251669412352214725103
FUNDING (000s)
Funding SourceTotalThru FY22Est FY23Total 6 YearsFY 24FY 25FY 26FY 27FY 28FY 29Beyond 6 Years
Municipal (WSSC Only)1763601254145601612178730213363309816791822
WSSC Bonds20826201246017252114840166593411148306381372046823281
Total Funding Sources22589801371418708116452184463713251669412352214725103
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request13714
Year First AppropriationFY11
Appropriation FY 24 Request16452
Last FY's Cost Estimate220994
Cumulative Appropriation172390
Expenditure / Encumbrances0
Unencumbered Balance172390