Description

This project supports the ongoing installation and maintenance of the information technology (IT) network infrastructure throughout all Montgomery College facilities, as well as on-premise server operations for applications not suitable for cloud computing. The network-related infrastructure includes cable distribution systems (conduit, fiber optics, wiring); equipment such as routers, switches, wireless access points, firewalls, intrusion detection and prevention devices; network management systems, specialized technology tools, monitoring systems, and diagnostic equipment; and remote access technologies. Also included are telephone systems, emergency notification systems, building management systems, and video security systems.

The scope of the project includes the associated electrical, environmental, and backup systems needed to ensure the reliable operation of all equipment. On-premise server operations are supported through the maintenance of a primary data center on the Takoma Park/Silver Spring (TP/SS) campus, and a backup data center on the Rockville campus. Associated with the TP/SS data center is the College's Network Operating Center (NOC), where staff maintain server and network equipment and provide 24/7 monitoring of all College IT systems and services to ensure proper functioning and performance. This includes instructional and administrative applications and all network and Internet-related services used in support of both credit and non-credit programs. This project funds six positions.

Note: The Network Operating Center/Datacenter project's (P076618) FY19 and beyond funding requests and work years have been added to this project. In addition, the project name has changed from Network Infrastructure Support Systems to Network Infrastructure and Server Operations.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$46.92M Total
Expenditures/Funding
$22.8M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Costs increase due to the addition of FY25 to FY26.
anchor

Justification

The College networks used for all forms of data, voice, video, and machine communication must be maintained and upgraded continuously to ensure no College location is without the necessary technology capabilities and support. This requires planned replacement and upgrades as technology evolves. As faculty continue to develop more learning programs and methods to meet the increased expectations of students, the technology needs also evolve and change. Without meeting the expectations and requirements developed in the various College strategic and master planning documents, the College will fall behind in its ability to provide needed technology at the appropriate time. State-of-the-market hardware and software capabilities and cloud services are required to attract and serve students, faculty and staff, as well as to serve the business community by upgrading work force technology skills and providing a base for continued economic development in the county. Information technology directly enables the College's mission and is used to facilitate student success; to effectively and efficiently operate the College; and to support the College's growth, development, and community initiatives.
anchor

Other

FY21 Appropriation: $3,300,000 (Current Revenue: General). FY22 Appropriation: $3,700,000 (Current Revenue: General). The following fund transfers/reductions have occurred with this project: By County Council Resolution No. 16-1261, the cumulative appropriation was reduced by $533,000 (Current Revenue: General) as part of the FY10 savings plan; $800,000 to the Network Operating Center project (#P076618)(BOT Resol. #12-06-037,6/11/12). FY19 reduction of $400,000 due to County affordability constraints.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

MC2025 Strategic Plan, Academic Master Plan 2016-2021, Collegewide Facilities Master Plan Update (6/18), Information Technology Master Plan, Student Affairs Master Plan 2018-2021, and campus building renovation projects. Expenditures are made in alignment with the priorities and guidelines establish by these documents.
Download & Explore
Budget Snapshot
$46.92M Total
Expenditures/Funding
$22.8M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP076619
Date Last Modified03/30/20
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision60643951103310801801801801801801800
Land00000000000
Site Improvements and Utilities00000000000
Construction2174157406001001001001001001000
Other38679136323927211203020342038203820352035200
Total Expenditures46917191574960228003300370041004100380038000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Current Revenue: General45497177374960228003300370041004100380038000
Recordation Tax14201420000000000
Total Funding Sources46917191574960228003300370041004100380038000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26
Full Time Equivalent (FTE) 666666
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request3300
Year First AppropriationFY07
Appropriation FY 22 Request3700
Last FY's Cost Estimate39317
Cumulative Appropriation24117
Expenditure / Encumbrances20876
Unencumbered Balance3241