Description

This project will provide needed modifications to specific areas of restroom facilities. A study was conducted in FY 2004 to evaluate restrooms for all schools that were built or renovated before 1985. Ratings were based upon visual inspections of the existing materials and fixtures as of August 1, 2003. Ratings also were based on conversations with the building services managers, principals, vice principals, and staffs about the existing conditions of the restroom facilities. The numeric rating for each school was based on an evaluation method using a preset number scale for the assessment of the existing plumbing fixtures, accessories, and room finish materials. In FY 2010, a second round of assessments were completed, which included a total of 110 schools, including holding facilities. BY FY 2018 all 110 schools assessed were completed. An FY 2019 appropriation was approved for the next phase of this project. An FY 2019 supplemental appropriation and offsetting reductions of $2 million were approved from this project to the current revitalization/expansion project for Seneca Valley High School. An FY 2020 appropriation and amendment to the adopted FY2019-2024 CIP was approved to address restroom facilities throughout the school system including plumbing fixtures, accessories, and room finish materials. An FY 2021 appropriation of $3 million was requested to continue this level of effort project and address restroom facilities systemwide. However, due to fiscal constraints, the County Council, in the adopted FY2021-2026 CIP, reduced the appropriation by $547,000 less than the Board of Education's request. An FY 2022 appropriation was approved to continue this level of effort project. An FY 2023 appropriation was approved to address restroom facilities throughout the school system including plumbing fixtures, accessories, and room finish materials. An FY2024 appropriation is requested to continue this level of effort project.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$47.16M Total
Expenditures/Funding
$18M 6 Year Total
Expenditures/Funding
Budget Snapshot
$47.16M Total
Expenditures/Funding
$18M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP056501
Date Last Modified11/18/22
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision74202136198433005505505505505505500
Land00000000000
Site Improvements and Utilities00000000000
Construction39738186846354147002450245024502450245024500
Other00000000000
Total Expenditures47158208208338180003000300030003000300030000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds47158208208338180003000300030003000300030000
Total Funding Sources47158208208338180003000300030003000300030000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request3000
Year First AppropriationFY05
Appropriation FY 24 Request3000
Last FY's Cost Estimate47158
Cumulative Appropriation32158
Expenditure / Encumbrances0
Unencumbered Balance32158
Partial Closeout 3070
Total Partial Closeout30700