Description

The Technology Modernization (Tech Mod) project is a key component of the Montgomery County Public School strategic technology plan, Educational Technology for 21st Century Learning. This plan builds upon the following four goals: students will use technology to become actively engaged in learning, schools will address the digital divide through equitable access to technology, staff will improve technology skills through professional development, and staff will use technology to improve productivity and results. An FY 2019 appropriation was approved to continue this project and the technology modernization program to our schools throughout the system. However, due to fiscal constraints, the County Council approved a reduction of $3.622 million in FY 2019 from the Board of Education's request. An FY 2020 appropriation was approved to continue this project; however, due to fiscal constraints, the County Council shifted expenditures from FY 2021 and FY 2022 to FY 2023 and FY 2024. An FY 2021 appropriation was approved to continue this project and provide technology modernization to schools throughout the system. However, due to fiscal constraints, the County Council, in the adopted FY2021-2026 CIP, reduced the FY2021 and FY2022 expenditures for this project with respect the Board of Education's request. An FY 2022 appropriation was approved to continue this level of effort project and provide technology modernization to schools throughout the system. An FY 2023 appropriation was approved to continue this level of effort project and provide technology modernization to schools systemwide.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$527.53M Total
Expenditures/Funding
$153.41M 6 Year Total
Expenditures/Funding
anchor

Fiscal Note

FY19 and FY20 funding switch between Recordation Tax and Current Revenue General for $10,296,000 and $6,280,000 respectively. FY21 reduction in requested Current Revenue: General for $3.616 million and in FY22 for $1.0 million with the assumption that in FY21 there will be $1.2 million in Federal E-Rate.

FY21 supplemental for $1,815,267 under Federal E-Rate Reimbursement

anchor

Coordination

FY 2023 -- Salaries and Wages: $5M, Fringe Benefits: $893K, Workyears: 36.5 FY 2024-2028 -- Salaries and Wages $24M, Fringe Benefits $5M, Workyears: 182.5.
Download & Explore
Budget Snapshot
$527.53M Total
Expenditures/Funding
$153.41M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP036510
Date Last Modified05/20/22
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision527527345251288661534102674626664250002500025000250000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures527527345251288661534102674626664250002500025000250000
FUNDING (000s)
Funding SourceTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Current Revenue: General23499384542161651342862099526623232312154422401194920
Federal Aid2518425695-51100000000
Recordation Tax267350235014132121912457514117693456259955080
Total Funding Sources527527345251288661534102674626664250002500025000250000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request26746
Year First AppropriationFY03
Appropriation FY 24 Request26664
Last FY's Cost Estimate476221
Cumulative Appropriation378010
Expenditure / Encumbrances0
Unencumbered Balance378010