Description

This project addresses sprinklers, escape windows, exit signs, fire alarm devices, exit stairs, and hood and fire suppression systems to comply with annual Fire Marshal inspections. An FY 2011 appropriation was approved to continue this program to maintain code compliance and life-cycle equipment replacement. An FY 2012 appropriation was approved to continue this level of effort project. An FY 2013 appropriation was approved to maintain life safety code compliance and equipment life-cycle replacements at MCPS facilities systemwide. An FY 2014 appropriation was approved to continue this project. An FY 2015 appropriation was approved to continue this level of effort project and maintain life safety code compliance through equipment replacement such as fire alarm systems that will be over 20 years old and will have exceeded their anticipated life-cycle. An FY 2016 appropriation was approved to continue this level of effort project. An FY 2017 appropriation was approved to continue this level of effort project as well as address code compliance issues related to the storage of flammable materials at schools systemwide. An FY 2018 appropriation was approved to continue this project. An FY 2019 appropriation was approved to continue this level of effort project. An FY 2020 appropriation was approved to continue this level of effort project. An FY 2021 appropriation was approved to continue this project to address code compliance issues systemwide. An FY 2022 appropriation was approved to continue this level of effort project to maintain life safety code compliance and life-cycle replacement of equipment systemwide.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$24.5M Total
Expenditures/Funding
$4.9M 6 Year Total
Expenditures/Funding
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Fire Marshal
Download & Explore
Budget Snapshot
$24.5M Total
Expenditures/Funding
$4.9M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP016532
Date Last Modified05/22/21
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision262216821008401401401401401401400
Land00000000000
Site Improvements and Utilities00000000000
Construction2188015374244440626776776776776776770
Other00000000000
Total Expenditures2450217056254449028178178178178178170
FUNDING (000s)
Funding SourceTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds2450217056254449028178178178178178170
Total Funding Sources2450217056254449028178178178178178170
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request817
Year First AppropriationFY01
Appropriation FY 22 Request817
Last FY's Cost Estimate26656
Cumulative Appropriation20417
Expenditure / Encumbrances0
Unencumbered Balance20417
Partial Closeout 2095
New Partial Closeout2154
Total Partial Closeout20952154