Description

This project provides for the systematic replacement of heating, ventilating, air conditioning, automated temperature controls, and plumbing systems for MCPS facilities. This replacement approach is based on indoor environmental quality (IEQ), energy performance, maintenance data, and the revitalization/expansion schedule. Qualifying systems and/or components are selected based on the above criteria and are prioritized within the CIP through a rating system formula. MCPS is participating in interagency planning and review to share successful and cost effective approaches. For projects on the revitalization/expansion schedule, the scope is reduced to the minimum necessary to maintain the operation of the existing mechanical system.  Any new equipment installations will be salvaged at the time of the revitalization/expansion project and will be re-used. The County Council, in the adopted FY 2013-2018 CIP, significantly reduced the expenditures requested by the Board of Education for this project for FY 2014 and beyond. An FY 2014 appropriation and amendment to the FY 2013-2018 CIP was requested to provide an additional $11.46 million above the adopted CIP to reinstate funds that were removed by the County Council during reconciliation in May 2012. However, the County Council, in the adopted FY 2013-2018 Amended CIP, approved only $3.82 million of the $11.46 million requested by the Board. Due to fiscal constraints, the County Council adopted FY 2015-2020 CIP reduced the FY 2016 expenditures requested by the Board of Education from $28 million to $16 million, but increased the outyears by a total of $8 million ($2 million in FYs 2017-2020). An FY 2015 appropriation was approved for mechanical systems upgrades and/or replacements at 3 high schools, 3 middle schools, and 11 elementary schools. An FY 2016 appropriation was approved for mechanical systems upgrades and/or replacements at Quince Orchard (Phase II) and Damascus (Phase III) high schools; Shady Grove (Phase II) Middle School; and Beall, Burning Tree, Captain Daly, Highland, and Rolling Terrace elementary schools. An FY 2017 appropriation was approved, but was $3 million less than the Board of Education's request. The funds will be used for mechanical systems upgrades and/or replacements at John T. Baker (Phase I) and Silver Spring International middle schools; and Greencastle, Olney, Greenwood, Jones Lane, Stone Mill, Brooke Grove, Clearspring, Laytonsville, New Hampshire Estates, and Sligo Creek elementary schools. An FY 2018 appropriation was approved for mechanical systems upgrades and/or replacements at John T. Baker (Phase II), Briggs Chaney (Phase I), and Silver Spring International middle schools; and Jones Lane, Lois P. Rockwell, and Stone Mill elementary schools.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$201.93M Total
Expenditures/Funding
$153M 6 Year Total
Expenditures/Funding
anchor

Disclosures

Expenditures will continue indefinitely. MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

CIP Master Plan for School Facilities
Download & Explore
Budget Snapshot
$201.93M Total
Expenditures/Funding
$153M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP816633
Date Last Modified
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY16Rem FY16Total 6 YearsFY 17FY 18FY 19FY 20FY 21FY 22Beyond 6 Years
Planning, Design and Supervision3670051002100295005000300030006000600065000
Land00000000000
Site Improvements and Utilities00000000000
Construction1652323406076721235002300015000150002250022000260000
Other00000000000
Total Expenditures2019323916097721530002800018000180002850028000325000
FUNDING (000s)
Funding SourceTotalThru FY16Rem FY16Total 6 YearsFY 17FY 18FY 19FY 20FY 21FY 22Beyond 6 Years
Current Revenue: General10000010001000000000
G.O. Bonds183434391602501440242158515439180002850028000325000
State Aid174980952279765415256100000
Total Funding Sources2019323916097721530002800018000180002850028000325000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 17 Request28000
Year First AppropriationFY81
Appropriation FY 18 Request18000
Last FY's Cost Estimate16388
Cumulative Appropriation76932
Expenditure / Encumbrances39160
Unencumbered Balance37772
Partial Closeout 119883
New Partial Closeout22745
Total Partial Closeout11988322745