Description

This level of effort project is intended to provide a structured process to ensure that all recreation indoor pool facilities are refurbished through repair or replacement of facility components. A facility assessment will be conducted to evaluate the level of repair or replacement for each facility and create a program of requirements with an associated construction cost estimate.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$6.81M Total
Expenditures/Funding
$5.62M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

The Department of Recreation will identify the facilities and scope of the work through a facility assessment prior to the design and construction process. Projects will be prioritized based on facility assessment results and programmatic needs. Refurbishment for the Kennedy Shriver Aquatic Center is under construction, and planning for the Olney Indoor Swim Center will start in FY27, with construction planned to begin in FY29.
anchor

Cost Change

Cost updated to reflect a new implementation cost and schedule.
anchor

Justification

Many County indoor pool facilities have not been updated in many years. This project will ensure that: 1) the County's capital investments at indoor swim facilities are protected by maintaining the department's infrastructure, 2) all new and required construction codes are addressed and implemented, 3) critical equipment and building systems are overhauled or replaced prior to failure, and 4) reorganization of internal space is completed to ensure that space is fully utilized based on the community's needs for programs and services.
anchor

Other

Notice identifying the specific recreation projects that will be refurbished must be provided to the Council at least 60 days before any funding is obligated or spent. The notice to Council must include the scope of work, cost estimate, and expenditure schedule for planning, design, and supervision, construction and other costs by fiscal year.
anchor

Coordination

Department of General Services, Department of Recreation
Download & Explore Project Details
Budget Snapshot
$6.81M Total
Expenditures/Funding
$5.62M 6 Year Total
Expenditures/Funding
anchor
Project NumberP722506
Date Last Modified12/31/25
Administering AgencyRecreation
CategoryCulture and Recreation
SubCategoryRecreation
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision141700141743418740928010700
Land350035002015000
Site Improvements and Utilities00000000000
Construction51001181039190022861633000
Other2540025400148106000
Total Expenditures68061181056254341872863203410700
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds68061181056254341872863203410700
Recordation Tax Premium (MCG)00000000000
Total Funding Sources68061181056254341872863203410700
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY25
Appropriation FY 28 Request0
Last FY's Cost Estimate17646
Cumulative Appropriation1963
Expenditure / Encumbrances1201
Unencumbered Balance762