up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for planning and preliminary engineering design for new and reconstructed pedestrian facility and bikeway projects under consideration for inclusion in the Capital Improvements Program (CIP). Prior to the establishment of a stand-alone project in the CIP, the Department of Transportation will perform Phase I of facility planning, a rigorous planning-level investigation of the following critical project elements: purpose and need; usage forecasts; traffic operational analysis; community, economic, social, environmental, and historic impact analyses; recommended concept design and public participation are considered. At the end of Phase I, the Transportation, Infrastructure, Energy and Environment (T&E) Committee of the County Council reviews the work and determines if the project has the merits to advance to Phase II of facility planning: preliminary (35 percent level of completion) engineering design. In preliminary engineering design, construction plans are developed showing specific and detailed features of the project, from which its impacts and costs can be more accurately assessed. At the completion of Phase II, the County Executive and County Council hold project-specific public hearings to determine if the candidate project merits consideration in the CIP as a funded stand-alone project.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$7.48M Total
Expenditures/Funding
$5.39M 6 Year Total
Expenditures/Funding
anchor

Cost Change

FY25-30 adjusted to account for inflation. FY29 and FY30 added to this Level of Effort project
anchor

Justification

There is a continuing need to define the scope and determine need, benefits, implementation feasibility, horizontal and vertical alignments, typical sections, impacts, community support/opposition, preliminary costs, and alternatives for master planned transportation recommendations. Facility Planning provides decision makers with reliable information to determine if a master-planned transportation recommendation merits inclusion in the CIP as a stand-alone project. The sidewalk and bikeway projects in Facility Planning specifically address pedestrian needs.
anchor

Fiscal Note

Beginning in FY23, this project splits the original Facility Planning - Transportation (P509337) into three separate facility planning projects by mode: Facility Planning - Roads (P509337), Facility Planning - Mass Transit (P502308), and Facility Planning - Pedestrian Facilities and Bikeways (P502312).
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress. Expenditures will continue indefinitely.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Maryland DOT State Highway Administration, Maryland Department of the Environment, Maryland Department of Natural Resources, U.S. Army Corps of Engineers, Department of Permitting Services, Utilities, Municipalities, affected communities, Commission on Aging, Commission on People with Disabilities, Montgomery County Pedestrian Safety Advisory Committee

Download & Explore
Budget Snapshot
$7.48M Total
Expenditures/Funding
$5.39M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502312
Date Last Modified02/29/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision7478271181453931049677614101510969420
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures7478271181453931049677614101510969420
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Current Revenue: General7478271181453931049677614101510969420
Total Funding Sources7478271181453931049677614101510969420
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request1049
Year First AppropriationFY23
Appropriation FY 26 Request677
Last FY's Cost Estimate7280
Cumulative Appropriation2085
Expenditure / Encumbrances966
Unencumbered Balance1119