anchor

Description

This project provides for permanent patching of residential/rural roads in older residential communities. This permanent patching program provides for deep patching of residential and rural roads to restore limited structural integrity and prolong pavement performance. This program will ensure structural viability of older residential pavements until such a time that road rehabilitation occurs. Based on current funding trends, many residential roads identified as needing reconstruction may not be addressed for 40 years or longer. The permanent patching program is designed to address this problem. Pavement reconstruction involves either total removal and reconstruction of the pavement section or extensive deep patching followed by grinding along with a thick structural hot mix asphalt overlay. Permanent patching may improve the pavement rating such that total rehabilitation may be considered in lieu of total reconstruction, at significant overall savings.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$92.94M Total
Expenditures/Funding
$36.53M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost change is due to increases in unit costs for materials and contractual labor, an increase in funding levels to more closely match the current countywide Pavement Condition Index (PCI) for residential and rural roads, as well as adding FY31 and FY32 to this Level of Effort project.
anchor

Justification

In FY09, the Department of Transportation instituted a pavement management system. This system provides for systematic physical condition surveys. The physical condition surveys note the type, level, and extent of residential pavement deterioration combined with average daily traffic and other usage characteristics. This information is used to calculate specific pavement ratings, types of repair strategies needed, and associated repair costs, as well as the overall Pavement Condition Index (PCI) of the entire residential network. The system also provides for budget optimization and a systematic approach to maintaining a healthy residential pavement inventory. The updated 2024 pavement condition survey indicated that 499 lane-miles (12 percent) of residential pavement have fallen into the lowest possible category and are in need of structural patching. Typically, pavements rated in this category require between 15-20 percent permanent patching per lane-mile. Physical condition inspections of residential pavements will occur on a 2-year cycle.
anchor

Fiscal Note

$56.7 million is the total annual funding amount required across the 3 residential & rural road CIP projects (Permanent Patching, Rehabilitation, and Resurfacing) to maintain the current Countywide Pavement Condition Index of 68 for residential and rural roads. Related CIP projects include Residential and Rural Road Rehabilitation (No. 500914) and Resurfacing: Residential/Rural Roads (No. 500511). Funding switch replacing Contributions and a portion of GO Bonds with Land Sale Proceeds in FY25. Funding switch from GO bonds to GO bonds premium for $2.5 million in FY27.
anchor

Disclosures

Expenditures will continue indefinitely. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

WSSC Water, Other Utilities, Montgomery County Department of Housing and Community Affairs, Montgomery County Public Schools, Maryland - National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Regional Services Centers, Community Associations, Montgomery County Pedestrian Safety Advisory Committee, Commission on People with Disabilities.
Download & Explore Project Details
Budget Snapshot
$92.94M Total
Expenditures/Funding
$36.53M 6 Year Total
Expenditures/Funding
anchor
Project NumberP501106
Date Last Modified01/10/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryHighway Maintenance
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision7102986562281038103810381038103810380
Land00000000000
Site Improvements and Utilities00000000000
Construction85829528332692303045884488448844884488448840
Other77000000000
Total Expenditures92938528493557365326922592259225922592259220
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bond Premium35001000025002500000000
G.O. Bonds85417478283557340324422592259225922592259220
Recordation Tax Premium (MCG)30293029000000000
State Aid992992000000000
Total Funding Sources92938528493557365326922592259225922592259220
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request6922
Year First AppropriationFY11
Appropriation FY 28 Request5922
Last FY's Cost Estimate70034
Cumulative Appropriation56406
Expenditure / Encumbrances52911
Unencumbered Balance3495