Description

This project provides for permanent patching of residential/rural roads in older residential communities. This permanent patching program provides for deep patching of residential and rural roads to restore limited structural integrity and prolong pavement performance. This program will ensure structural viability of older residential pavements until such a time that road rehabilitation occurs. Based on current funding trends, many residential roads identified as needing reconstruction may not be addressed for 40 years or longer. The permanent patching program is designed to address this problem. Pavement reconstruction involves either total removal and reconstruction of the pavement section or extensive deep patching followed by grinding along with a thick structural hot mix asphalt overlay. Permanent patching may improve the pavement rating such that total rehabilitation may be considered in lieu of total reconstruction, at significant overall savings.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$70.03M Total
Expenditures/Funding
$20.44M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase is due to inflation and the addition of funding in FY29 and FY30.
anchor

Justification

In FY09, the Department of Transportation instituted a pavement management system. This system provides for systematic physical condition surveys. The physical condition surveys note the type, level, and extent of residential pavement deterioration combined with average daily traffic and other usage characteristics. This information is used to calculate specific pavement ratings, types of repair strategies needed, and associated repair costs, as well as the overall Pavement Condition Index (PCI) of the entire residential network. The system also provides for budget optimization and a systematic approach to maintaining a healthy residential pavement inventory. The updated 2022 pavement condition survey indicated that 702 lane-miles (16 percent) of residential pavement have fallen into the lowest possible category and are in need of structural patching. Typically, pavements rated in this category require between 15-20 percent permanent patching per lane-mile. Physical condition inspections of residential pavements will occur on a 2-3 year cycle.
anchor

Fiscal Note

$63.0 million is the annual cost required to maintain the current Countywide Pavement Condition Index of 67 for residential and rural roads. $66.0 million is the annual requirement to achieve a Countywide Pavement Condition Index of 70 for residential and rural roads. Related CIP projects include Residential and Rural Road Rehabilitation (No. 500914) and Resurfacing: Residential/Rural Roads (No. 500511). In FY21, there was a funding switch utilizing GO Bonds, of which, $1 million was allocated in GO Bond Premium.
anchor

Disclosures

Expenditures will continue indefinitely. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Maryland State Highway Administration, Utility Companies, Montgomery County Department of Permitting Services, City of Gaithersburg, Facility Planning: Transportation (CIP No. 509337).
Download & Explore
Budget Snapshot
$70.03M Total
Expenditures/Funding
$20.44M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP501106
Date Last Modified02/21/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryHighway Maintenance
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision366092093155843533322811984350
Land00000000000
Site Improvements and Utilities00000000000
Construction66367462261257188842972307431793288339929720
Other77000000000
Total Expenditures70034462423350204423407340734073407340734070
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bond Premium10001000000000000
G.O. Bonds68042442503350204423407340734073407340734070
State Aid992992000000000
Total Funding Sources70034462423350204423407340734073407340734070
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request3407
Year First AppropriationFY11
Appropriation FY 26 Request3407
Last FY's Cost Estimate62192
Cumulative Appropriation49592
Expenditure / Encumbrances46340
Unencumbered Balance3252