Description

This project provides for planning, design, and construction of a new 28,294 gross square feet 6th District Police Station and a new parking garage of 59,526 gross square feet in two levels to serve Gaithersburg/Montgomery Village and vicinity. The station will be in a new development located on the extension of Watkins Mill Road between I-270 and MD 355. The new station will contain two floors and parking for the public and staff. The first floor will house the public access area, operations, patrol and support functions, and a small prisoner holding area. The station will serve as the base for the Central Traffic Unit (CTU) that was established in July 2021. The second floor will house four special teams, including investigative units, patrol sergeant offices, staff support, administration, and an exercise room. Besides a surface parking lot that will provide 30 parking spaces in the non-secured area, a two-level parking garage to accommodate 148 cars will be constructed inside the secured area. This parking garage will house a large evidence room, a vehicle service bay, and storage areas for police bicycles, road flares, and the CTU's 29 motorcycles. The district station is a 24-hour per day, 7-day per week operation and provides support for beat teams. It is the command center for any satellite facilities within the police district. The district station will accommodate up to 178 department staff and volunteers. It has been sized to meet the needs projected in the Police Chief's Staffing Plan within the 6th district. A public meeting room on the first floor will be available to facilitate outreach with the community.
project image
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$38.01M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Construction completed in April 2025.
anchor

Cost Change

Cost increase due to need to reimburse contractor for proportional share of infrastructure development costs.
anchor

Justification

The current facility is in rented space and lacks several features of a modern police station, including reinforced interview rooms and a dedicated sally port.
anchor

Other

Special Capital Projects Legislation [Bill No. 13-05] was adopted by Council June 28, 2005. Reauthorization [Bill No. 26-10] was adopted by Council June 15, 2010. Reauthorization [Bill No. 16-22] was adopted by Council July 25, 2022.
anchor

Fiscal Note

FY23 supplemental appropriation of $5.941 million in GO bonds. FY 24: Funding switch between GO bonds and GO bond premium in the prior to the 6-year period for $11.7 million. FY25 funding switch from GO bonds to GO bond premium for $10 million. FY26 transfer for $161,158 (GO bonds) from Female Facility Upgrade to 6th District Police Station.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Department of Police, Department of General Services, Department of Permitting Services, Department of Technology and Enterprise Business Solutions, Upcounty Regional Services Center, Police Facilities Plan, Local Law Enforcement Agencies, State Highway Administration, Department of Environmental Protection, Verizon, Maryland Department of Natural Resources, City of Gaithersburg, WSSC Water, Potomac Electric Power Company (Pepco), and Washington Gas.
Budget Snapshot
$38.01M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP470301
Date Last Modified12/29/25
Administering AgencyGeneral Services
CategoryPublic Safety
SubCategoryPolice
Planning AreaGaithersburg and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision5544536817600000000
Land2020000000000
Site Improvements and Utilities1729497123200000000
Construction2831928319000000000
Other2397223616100000000
Total Expenditures3800936440156900000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bond Premium2065020650000000000
G.O. Bonds72765707156900000000
PAYGO1008310083000000000
Total Funding Sources3800936440156900000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance2226371371371371371371
Energy1950325325325325325325
NET IMPACT4176696696696696696696
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY06
Appropriation FY 28 Request0
Last FY's Cost Estimate37848
Cumulative Appropriation38009
Expenditure / Encumbrances36810
Unencumbered Balance1199