up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides funding for the modernization and/or replacement of existing elevators on all three campuses.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$6.93M Total
Expenditures/Funding
$1.05M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Increase due to addition of FY29 and FY30.
anchor

Justification

Many elevator systems at the College are inefficient, outdated and beyond continued economic repair. While the College's maintenance program has kept elevators operational, spare parts are not readily available from maintenance providers for many of the older pieces of elevator equipment. This results in extended down time, high maintenance costs, higher energy consumption, and the lack of current car safety devices. This project will modernize elevators to improve overall performance, safety, reliability and energy conservation, and to achieve code compliance. Furthermore, some buildings lack elevators or have elevators of inadequate size requiring the installation of new elevators to increase accessibility and capacity. Related studies include the Montgomery College Strategic Plan (7/23), Collegewide Facilities Condition Assessment (1/23), a Collegewide Elevator Study (4/05), the Collegewide Facilities Master Plan (Pending 2023), and the Takoma Park/Silver Spring Elevator Update (9/09).
anchor

Other

FY25 Appropriation: $54,000 (G.O. Bonds). FY26 Appropriation: $200,000 (G.O. Bonds).
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

This project is coordinated with the scheduled building renovations on the Rockville, Takoma Park/Silver Spring and Germantown Campuses., Phase 4 - Takoma Park/Silver Spring Elevator Study, Site Improvements: College (CIP No. P076601)
Download & Explore
Budget Snapshot
$6.93M Total
Expenditures/Funding
$1.05M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP056608
Date Last Modified09/18/23
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision73362610700000000
Land00000000000
Site Improvements and Utilities00000000000
Construction620142329151054542002002002002000
Other00000000000
Total Expenditures6934485810221054542002002002002000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds6934485810221054542002002002002000
Total Funding Sources6934485810221054542002002002002000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request54
Year First AppropriationFY03
Appropriation FY 26 Request200
Last FY's Cost Estimate6534
Cumulative Appropriation5880
Expenditure / Encumbrances4858
Unencumbered Balance1022