up
Budget Year / Version:  
anchor
anchor
anchor

Description

Based on the KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP included funding for a Major Capital Project at this school. It is anticipated that this Major Capital Project will include a significant addition that both addresses programmatic requirements, as well as increases capacity. Due to fiscal constraints, the County Council, in the adopted FY2021-2026 CIP approved the completion date for this project one year beyond the Board of Education's request. An FY 2023 appropriation was approved for the architectural planning and design for this project. An FY 2024 appropriation was approved for construction funds. As part of the Board of Education's Requested FY2025-2030 CIP, the construction timeline for this project was extended one-year. Therefore, this Major Capital Project was scheduled to be completed August 2027. However, due to fiscal constraints, as part of the County Council's approved FY2025-2030 CIP, construction expenditures were shifted to the outyears of the CIP with a "to be determined" completion date. An appropriation for construction funds will be considered in a future CIP.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$201.87M Total
Expenditures/Funding
$97.63M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the IAC Capital Improvement Program or the Built To Learn Act for school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$201.87M Total
Expenditures/Funding
$97.63M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP652114
Date Last Modified05/16/24
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaDamascus and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision52802894816175958000000
Land00000000000
Site Improvements and Utilities110290395870713571350000000
Construction18346005000894820000316385784488978
Other21000090400003705341196
Total Expenditures20186928913774976323666358000320085837890174
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds13791428913774629363666358000146894100160915
State Aid6395500346960000173191737729259
Total Funding Sources20186928913774976323666358000320085837890174
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY23
Appropriation FY 26 Request0
Last FY's Cost Estimate127911
Cumulative Appropriation125811
Expenditure / Encumbrances0
Unencumbered Balance125811