Description

This project provides for the rehabilitation and/or renovation of existing park roads, including Sligo Creek Parkway, Beach Drive, and Little Falls Parkway. Improvements may include pavement renovation, traffic calming, drainage improvements, traffic controls, guardrails/barriers, shoulder improvements, pedestrian/trail connections, pull-off/parking improvements, roadside safety improvements, etc.

anchor

Phase

Ongoing

Status

New
anchor
Budget Snapshot
$2.45M Total
Expenditures/Funding
$2.45M 6 Year Total
Expenditures/Funding
anchor

Fiscal Note

Funding transferred from MCDOT for the responsibility of Parks to maintain these parkways. Under the previous agreement these parkways were maintained by MCDOT.
anchor

Disclosures

Expenditures will continue indefinitely.
Download & Explore Project Details
Budget Snapshot
$2.45M Total
Expenditures/Funding
$2.45M 6 Year Total
Expenditures/Funding
anchor
Project NumberP872701
Date Last Modified01/10/26
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision300003005050505050500
Land00000000000
Site Improvements and Utilities21540021543593593593593593590
Construction00000000000
Other00000000000
Total Expenditures24540024544094094094094094090
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds24540024544094094094094094090
Total Funding Sources24540024544094094094094094090
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request409
Year First Appropriation
Appropriation FY 28 Request409
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0