This project provides for the design and implementation of energy savings projects in various County facilities and locations using funds obtained through the merger of Exelon Corporation, Pepco Holdings, Inc., Potomac Electric Power Company, and Delmarva Power & Light Company ("Exelon/PHI merger"), approved by the Maryland Public Service Commission (PSC) per Order No. 86990 on May 15, 2015. Projects include lighting retrofits, heating, ventilation, and cooling (HVAC) controls upgrades and equipment replacement including chillers, condensing units and air handling units.
anchor

Phase

Ongoing

Status

Pending Closeout
anchor
Budget Snapshot
$7.34M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Projects are identified and scheduled based on energy savings potential, reduced maintenance costs, overall cost savings, and quantifiable environmental benefits. Schedule is subject to change based on project need. Currently planned projects include:

Completed FY23: Animal Shelter, Circuit Court North Tower, Clara Barton Neighborhood Recreation Center, Colesville Depot, Gwendolyn Coffield Community Recreation Center, Holiday Park Senior Center, Materials Management Warehouse, Public Safety Communication Center, Warehouse Center, White Oak Community Recreation Center.

FY24: Circuit Court South Tower, Brigadier General Charles McGee Library, Fire Station 31, Lone Oak Center, 600 East Gude Drive, Mid-County Community Recreation Center, Public Safety Training Academy, Public Safety Headquarters, Ross Boddy Community Recreation Center, Wheaton Rescue Squad #2.
anchor

Cost Change

FY24 supplemental in Utility Merger Funds for the amount of $504,662.
anchor

Justification

The Exelon/PHI (PHI) merger, approved by the Maryland PSC per Order No. 86990 on May 15, 2015 and Order No. 88128 on April 12, 2017 regarding the Most Favored Nation Provision, resulted in the County receiving over $40 million, of which $8.4 million was designated to establish a Green Sustainability Fund. The County will use $6.7 million of these funds for this project to establish energy savings projects in public facilities. Generally, projects will pay for themselves over several years. Significant reductions in energy consumption, greenhouse gas emissions, and maintenance are expected.
anchor

Fiscal Note

A total of $6.7 million was originally appropriated in the Restricted Donation Fund in FY19. Approximately $500,000 was spent in FY20 from the Restricted Donation Fund to fund the initial round of projects, including Potomac Library, Upper County Community Recreation Center and Pool, Bethesda-Chevy Chase Regional Services Center, and Margaret Schweinhaut Senior Center. The remaining funds of $6.2 million shifted to this new CIP project.

Projects are also expected to be eligible for utility incentives during and after implementation; utility incentives will offset the use of the merger funds. Merger funds cannot be used to supplant existing County funding for projects, including staff charges.

FY23 Supplemental in Utility Merger Funds for the amount of $636,971.

FY24 supplemental in Utility Merger Funds for the amount of $504,662.
anchor

Coordination

Department of General Services, Department of Finance, Office of Management and Budget, Office of the County Attorney
Download & Explore
Budget Snapshot
$7.34M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP362105
Date Last Modified01/09/24
Administering AgencyGeneral Services
CategoryGeneral Government
SubCategoryCounty Offices and Other Improvements
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision7373000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction72694733253600000000
Other00000000000
Total Expenditures73424806253600000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Utility Merger Funds73424806253600000000
Total Funding Sources73424806253600000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY21
Appropriation FY 26 Request0
Last FY's Cost Estimate7342
Cumulative Appropriation7342
Expenditure / Encumbrances5554
Unencumbered Balance1788