Description

This program will provide for phased upgrades and modernization of computer aided dispatch (CAD), law enforcement records management system (RMS), and voice radio systems used primarily by the County's public safety first responder agencies including Police, Fire and Rescue, Sheriff, Corrections and Rehabilitation, and Emergency Management and Homeland Security. The modernization will include replacement of the current CAD/RMS system, replacement of public safety mobile and portable radios, upgrade of non-public safety mobile and portable radios, and replacement of core voice radio communications infrastructure. The previously approved Fire Station Alerting System Upgrades project (CIP #451000) was transferred to this project in order to coordinate the upgrades with the new CAD system. The alerting system upgrades will modernize the fire station alerting systems at 43 existing work sites, maintaining the ability to notify fire and rescue stations of emergencies. The alerting system, including audible and data signals, is essential for the notification of an emergency and the dispatch of appropriate response units from the County. As voice, data, and video are beginning to converge to a single platform, this project will provide a pathway to a modern public safety support infrastructure that will enable the County to leverage technology advances and provide efficient and reliable systems for first responders. This project will follow the methodologies and strategies presented in the Public Safety Systems Modernization (PSSM) plan completed in July 2009.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$109.76M Total
Expenditures/Funding
$1.64M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

The infrastructure update for the Public Safety Radio System was completed in March 2021. The installation of the desktop radio consoles for the Alternate Emergency Communications Center and CAD A3 integration will be completed by the end of FY24. The Law Enforcement Records Management System (LE-RMS) is in the preliminary implementation stages.
anchor

Justification

The public safety systems require modernization. Prior to replacement, the CAD system was reaching the end of useful life and did not meet the County's current operational requirements, impacting the response time of first responders to 9-1-1 calls. The CAD Roadmap Study, completed in March 2009, recommended replacement of the system to address existing shortcomings and prepare for the next generation 9-1-1 systems. The manufacturer's support for the voice radio system had to be phased out as of December 31, 2009. Beyond that date, the manufacturer will only continue to provide system support on an as available basis, but will not guarantee the availability of parts or technical resources. The CAD modernization initiated a detailed planning phase that included the use of industry experts to assist with business process analysis and to develop detailed business and technical requirements for the new CAD system. This process allowed the County to incorporate lessons learned and best practices from other jurisdictions. As more of the County's regional partners migrate to newer voice technologies, it will affect interoperable voice communications. To ensure that the County maintains reliable and effective public safety (voice radio) communications for the operations of its first responders and to sustain communications interoperability for seamless mutual aid among its regional partners, the County needed to implement a project to upgrade and modernize its portable and mobile radio units and subsequently the radio voice communications infrastructure. Acceleration of the public safety radio purchases was initiated to take advantage of a Partial Payment in Lieu of Re-Banding offer from Sprint/Nextel toward the financing of new, upgraded, P-25 compliant public safety radios and to meet the Federal Communications Commission (FCC) mandated 800 MHZ frequency rebanding requirements for nationwide public safety radio frequency interoperability. Now, the installation of the new core radio communication infrastructure is needed. The fire station alerting system upgrades were identified as a need under Section 5 of the MCFRS Master Plan (adopted by the County Council in October 2005) and detailed in the Station Alerting and Public Address (SA/PA) System for Fire/Rescue Stations, Rev 1, 2006. This project allows for the continuous and seamless functioning of the alerting systems within each fire station. A preliminary survey by DTS of existing conditions at all stations revealed system-wide concerns, including inadequate spare parts inventory and lack of available maintenance support for alerting systems.
anchor

Other

This project was previously located in the County Offices Sub-Category prior to FY25.
anchor

Fiscal Note

Funding in FY09 included Urban Area Security Initiative (UASI) grant funding of $2.055 million and Fire Act grant funding of $988,000. Funding schedule reflects FY18 supplemental adding $32,000 in Contributions for additional equipment required for Local Fire Rescue Departments (LFRDs ). FY18 funding switch is due to a transfer of Current Revenue General for $283,000 from Technology Modernization (MCG) project offset by an equal reduction in Short-term Financing. In FY22, a $2 million transfer was made to a new Dickerson Radio Tower project. In FY23, there was a funding switch of $293K in FY22 Short-term Financing to FY22 Recordation Tax Premium and $2.366 million in FY23 Short-term Financing switched to FY23 Current revenue since Software as a Service is not financeable.
anchor

Coordination

PSSM Executive Steering Committee, Executive Program Directors, Technology and Enterprise Business Solutions (TEBS), Department of Police, Montgomery County Fire and Rescue Service, Sheriff's Office, Department of Correction and Rehabilitation, Office of Emergency Management and Homeland Security, Department of Transportation , Department of Liquor Control, Montgomery County Public Schools (MCPS), Maryland-National Park and Planning Commission (M-NCPPC) Park Police, Washington Metropolitan Area Transit Authority (WMATA)
Download & Explore
Budget Snapshot
$109.76M Total
Expenditures/Funding
$1.64M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP340901
Date Last Modified01/09/24
Administering AgencyCounty Executive
CategoryGeneral Government
SubCategoryTechnology Services
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision5960582713300000000
Land00000000000
Site Improvements and Utilities00000000000
Construction55894543104600000000
Other98213929433625164576987600000
Total Expenditures1097621033134804164576987600000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Contributions3232000000000
Current Revenue: General12962102211096164576987600000
Federal Aid2947276817900000000
G.O. Bonds4825946312194700000000
PAYGO29022902000000000
Recordation Tax Premium (MCG)3093280029300000000
Short-Term Financing3956738278128900000000
Total Funding Sources1097621033134804164576987600000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30
Maintenance2527--624624624655
Program-Staff-------
Program-Other-------
NET IMPACT2527--624624624655
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY09
Appropriation FY 26 Request0
Last FY's Cost Estimate109762
Cumulative Appropriation109762
Expenditure / Encumbrances107657
Unencumbered Balance2105