THIS PROJECT WAS NOT APPROVED FOR THE FY21-26 CIP. This project funds the demolition of the north side of the Student Affairs and Science Building, and will rebuild it from 2 stories to three stories, which will be a net gain of 18,000 gross square feet to the building. The existing first floor programmatic functions are devoted mostly to Student Services, which will move to the new Germantown Student Services Center. The building is currently undergoing a two phase renovation and addition to convert and reconfigure the building to house the Department of Physics, Engineering and Math along with the Math, Physics and Engineering Learning (MAPEL) Center. Overall growth at the Germantown Campus in combination with the transition to lab instruction for mathematics and engineering expansion has created the demand for additional academic space. Based on student interest, enrollment trends, existing and projected County and State workforce needs, and the teaching and learning strategies, including the final report of The Governor's Science Technology Engineering Mathematics Task Force, Investing in STEM to Secure Maryland's Future, the Germantown Campus will be well positioned to meet the needs of its students and the region.
project image
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$0M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Justification

Under the application of the State space guidelines, the enrollment growth on the Germantown Campus has resulted in a significant instructional space deficit. The Germantown Campus has a 2028 projected instructional space deficit of 13,584 NASF and a total space deficit anticipated to be 149,079 NASF. In addition, this project will position the College to address workforce shortages in the Science, Technology, Engineering, and Mathematics fields. This project will impact local and Maryland workforce shortages through educating students to fill technical jobs. Relevant studies include the Montgomery College 2025 Strategic Plan, Collegewide Facilities Master Plan Update (6/18), and the Renovation/Addition to Sciences & Applied Studies Building at Montgomery College Germantown Campus, Part 1, Part 2 (3/11).
anchor

Other

FY21 Appropriation: 0. FY22 Appropriation:0.
anchor

Disclosures

Montgomery College asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Facility Planning: College (No. P886686), Germantown Science & Applied Studies Phase 1- Renov. (No. P136600), Energy Conservation: College (No. P816611), PLAR: College (No. P926659)
Download & Explore
Budget Snapshot
$0M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP662102
Date Last Modified05/15/20
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaGermantown and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures00000000000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds00000000000
State Aid00000000000
Total Funding Sources00000000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First Appropriation
Appropriation FY 22 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0