Budget Year / Version:  
anchor
anchor
anchor

Description

Projections indicate that enrollment will exceed capacity by the end of the six-year planning period. An FY 2025 appropriation is requested to begin the planning and design for this addition project. This project is scheduled to be completed August 2028.
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$18.22M Total
Expenditures/Funding
$18.22M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the IAC Capital Improvement Program or the Built to Learn Act for school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$18.22M Total
Expenditures/Funding
$18.22M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP652503
Date Last Modified03/19/24
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision215000215061012502900000
Land00000000000
Site Improvements and Utilities3360003360027106500000
Construction1205500120550125029505405245000
Other65000650006500000
Total Expenditures182150018215610521045405405245000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds13661001366161052104540269161000
State Aid45540045540002714184000
Total Funding Sources182150018215610521045405405245000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request2150
Year First Appropriation
Appropriation FY 26 Request14765
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0