anchor

Description

Based on the KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP includes funding for a Major Capital Project at this school. This project will address aging infrastructure and meet programmatic objectives. An appropriation will be requested in a future CIP for the architectural planning and design for this project. This Major Capital Project is scheduled to be completed September 2027.
project image
anchor

Phase

Status

Active
anchor
Budget Snapshot
$40.26M Total
Expenditures/Funding
$10.26M 6 Year Total
Expenditures/Funding
anchor

Location

Budget Snapshot
$40.26M Total
Expenditures/Funding
$10.26M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP652116
Date Last Modified11/16/20
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision315700315700030639400
Land00000000000
Site Improvements and Utilities53820053820000210332790
Construction2942100172100000172127700
Other23000000000002300
Total Expenditures40260001026000030632197500030000
FUNDING (000s)
Funding SourceTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds40260001026000030632197500030000
Total Funding Sources40260001026000030632197500030000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First Appropriation
Appropriation FY 22 Request0
Last FY's Cost Estimate40260
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0