Description

Projections indicate that enrollment at Parkland Middle School will exceed capacity by 180 seats by the end of the six-year planning period. Therefore, the Board of Education's requested FY 2019-2024 CIP included funds for an addition project at this school. An FY 2019 appropriation was requested to begin planning this project. This project was scheduled to be completed September 2021. However, due to fiscal constraints, the County Council approved a one-year delay for this project. The Board of Education, in the amended FY 2019-2024 CIP, requested an FY 2020 appropriation for planning funds. Due to fiscal constraints, the County Council approved a one-year delay for this project. An FY 2021 appropriation was approved for planning funds. An FY 2022 appropriation was approved for construction funds. As part of the FY2023-2028 CIP, an additional $3.6 million from the county executive's Prevailing Wage and Built to Learn Act PDFs was included in this project to maximize state aid. An FY 2023 appropriation was approved to complete this project. This project is scheduled to be completed August 2023.
project image
anchor

Phase

Under Construction

Status

Active
anchor
Budget Snapshot
$18.24M Total
Expenditures/Funding
$14.71M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the IAC Capital Improvement Program or the Built To Learn Act for school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Mandatory Referral - M-NCPPC, Department of Environmental Protection, Building Permits:, Code Review, Fire Marshall, Department of Transportation, Inspections, Sediment Control, Stormwater Management, WSSC Permits
Budget Snapshot
$18.24M Total
Expenditures/Funding
$14.71M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP651911
Date Last Modified12/20/22
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaAspen Hill and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision12408363237224812400000
Land00000000000
Site Improvements and Utilities210701080102752750000000
Construction1400101580124217081534000000
Other8900089026762300000
Total Expenditures182388362692147108123658700000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds1092483626927396710928700000
State Aid73140073141014630000000
Total Funding Sources182388362692147108123658700000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28
Maintenance348585858585858
Energy132222222222222
NET IMPACT480808080808080
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request4490
Year First AppropriationFY21
Appropriation FY 24 Request0
Last FY's Cost Estimate18238
Cumulative Appropriation18238
Expenditure / Encumbrances0
Unencumbered Balance18238