up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing bridge (M-0056) on Redland Road over Mill Creek. The existing single-span concrete slab bridge will be removed and replaced with a new prestressed concrete box beam superstructure and precast concrete abutments and wing walls. The new superstructure will be constructed in the same location. The project also includes approach roadway work at each end of the bridge as necessary to tie into the existing roadway. The bridge and road will be closed to traffic during construction. Accelerated bridge construction techniques will be utilized to minimize the disruption to the traveling public and local community.
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design was completed in FY25. Construction is scheduled to start in FY26 and be completed in FY27. The bridge and road will be closed to traffic from June 2026 to August 2026 during construction while schools are out of session.
anchor

Cost Change

Construction cost increases due to inflation and for utility relocations to minimize impacts to parkland.
anchor

Justification

The existing concrete deck is in need of reconstruction and the existing concrete abutments and slope protections and steel frames and bearings are in need of repairs. The 2019 inspection revealed spalls and cracks at the concrete deck, abutments and slope protections, and pack rust, corrosion, and delamination at the steel frames and bearings. The proposed bridge replacement is necessary to provide a safe roadway condition for the traveling public.
anchor

Fiscal Note

The design costs for this project are covered in the Bridge Design project (CIP No. 509132). Intergovernmental funding contribution from WSSC Water is for the water line relocation. Project does not qualify for federal aid since existing bridge span is less than 20' long. FY26 transfer in from the State Transportation Participation project (No. 500722) for $868,000 in GO Bonds.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland Department of Transportation, State Highway Administration, Maryland Department of the Environment, Maryland Historical Trust, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, and utility companies
Download & Explore Project Details
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor
Project NumberP502507
Date Last Modified01/10/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaUpper Rock Creek Watershed
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY27FY28FY29FY30FY31FY32
Maintenance25-55555
NET IMPACT25-55555
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request1028
Year First AppropriationFY25
Appropriation FY28 Request0
Last FY's Cost Estimate4000
Cumulative Appropriation4868
Expenditure / Encumbrances23
Unencumbered Balance4845
anchor
Download & Explore Project Details