up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing bridge (M-0056) on Redland Road over Mill Creek. The existing single-span concrete slab bridge will be removed and replaced with a new prestressed concrete box beam superstructure and precast concrete abutments and wing walls. The new superstructure will be constructed in the same location. The project also includes approach roadway work at each end of the bridge as necessary to tie into the existing roadway. The bridge and road will be closed to traffic during construction. Accelerated bridge construction techniques will be utilized to minimize the disruption to the traveling public and local community.
anchor

Phase

Final Design Stage

Status

New
anchor
Budget Snapshot
$4M Total
Expenditures/Funding
$4M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

The design of the project is expected to be completed in 2024. The construction is scheduled to start in the spring of 2025 and be completed in the fall of 2025. The bridge and road will be closed to traffic from June 2025 to August 2025 during construction while schools are out of session.
anchor

Justification

The existing concrete deck is in need of reconstruction and the existing concrete abutments and slope protections and steel frames and bearings are in need of repairs. The 2019 inspection revealed spalls and cracks at the concrete deck, abutments and slope protections, and pack rust, corrosion, and delamination at the steel frames and bearings. The proposed bridge replacement is necessary to provide a safe roadway condition for the traveling public.
anchor

Other

The design costs for this project are covered in the "Bridge Design" project (CIP No. 509132).
anchor

Fiscal Note

Intergovernmental funding contribution from WSSC Water for water line relocation is anticipated. Relocation cost and contribution amount will be updated during the final design phase.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland Department of Transportation State Highway Administration, Maryland Department of the Environment, Maryland Historical Trust, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, and Utility Companies.
Budget Snapshot
$4M Total
Expenditures/Funding
$4M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502507
Date Last Modified01/08/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaUpper Rock Creek Watershed
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision8510085113971200000
Land83008383000000
Site Improvements and Utilities30000300300000000
Construction2766002766691207500000
Other00000000000
Total Expenditures40000040001213278700000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds38500038501063278700000
Intergovernmental15000150150000000
Total Funding Sources40000040001213278700000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request4000
Year First AppropriationFY25
Appropriation FY 26 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0