This project provides for the design and construction of a roadway extension of North High Street to Morningwood Drive in Olney. The project also provides a continuous 6-foot sidewalk on the south side of North High Street and ADA-compliant pedestrian access from Morningwood Drive.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$2.17M Total
Expenditures/Funding
$2.17M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design, land acquisition, and utility relocation will begin in FY23. The construction will begin in FY24.
anchor

Justification

The purpose of the project is to improve safety and enhance connectivity within the Olney town center vicinity. This project is supported by the Greater Olney Civic Association and will provide vehicular, pedestrian, and bicycle access to North High Street from Morningwood Drive instead of Georgia Avenue. This project also supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities on all roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Department of Permitting Services, Greater Olney Civic Association (GOCA), Olney Town Center Advisory Committee (OTCAC).
Budget Snapshot
$2.17M Total
Expenditures/Funding
$2.17M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502310
Date Last Modified06/09/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaOlney and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision55100551287861780000
Land44000440440000000
Site Improvements and Utilities11000110110000000
Construction106800106803267420000
Other00000000000
Total Expenditures21690021698374129200000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds21690021698374129200000
Total Funding Sources21690021698374129200000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request837
Year First AppropriationFY23
Appropriation FY 24 Request1332
Last FY's Cost Estimate2169
Cumulative Appropriation837
Expenditure / Encumbrances0
Unencumbered Balance837