Description

This project provides for the design and construction of a roadway extension of North High Street to Morningwood Drive in Olney. The project also provides a continuous 6-foot sidewalk on the south side of North High Street and ADA-compliant pedestrian access from Morningwood Drive.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$2.42M Total
Expenditures/Funding
$1.58M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design began in FY23 and will be completed in FY24. Land acquisition will begin in FY24 and construction will be completed in FY26.
anchor

Cost Change

Cost increase for design.
anchor

Justification

The purpose of the project is to improve safety and enhance connectivity within the Olney town center vicinity. This project is supported by the Greater Olney Civic Association and will provide vehicular, pedestrian, and bicycle access to North High Street from Morningwood Drive instead of Georgia Avenue. This project also supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities on all roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Department of Permitting Services, Greater Olney Civic Association (GOCA), Olney Town Center Advisory Committee (OTCAC).
Download & Explore
Budget Snapshot
$2.42M Total
Expenditures/Funding
$1.58M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502310
Date Last Modified05/16/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaOlney and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision801425811787810000000
Land44002142262620000000
Site Improvements and Utilities11000110011000000
Construction10680010680106800000
Other00000000000
Total Expenditures2419427951582104147800000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds2419427951582104147800000
Total Funding Sources2419427951582104147800000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request250
Year First AppropriationFY23
Appropriation FY 26 Request0
Last FY's Cost Estimate2169
Cumulative Appropriation2169
Expenditure / Encumbrances82
Unencumbered Balance2087