up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the design and construction of a new eight-to ten-foot wide sidepath for 3.3 miles along Bowie Mill Road from Olney Laytonsville Road (MD 108) to Muncaster Mill Road (MD 115) and continues along Muncaster Mill Road to Needwood Road. The project also provides a new pedestrian bridge over Rock Creek North Branch for continuation of the sidepath along Bowie Mill Road.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$30.33M Total
Expenditures/Funding
$25.99M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design started in FY23 and will be completed in FY26. Land acquisition will be completed in FY27 and utility relocation and construction will be completed in FY29.
anchor

Justification

The Montgomery County Bicycle Master Plan, approved in November 2018, recommends a sidepath along Bowie Mill Road. The project is a critical connection in the existing bicycle network between the existing trails and important destinations including Needwood Road Bike Path, North Branch Trail, the Inter-County Connector (ICC) Trail, Shady Grove Metro Station, Sequoyah Elementary School, Colonel Zadok Magruder High School, and Olney Town Center.
anchor

Other

This project will help the County to achieve its Vision Zero goals to reduce injuries and fatalities on county roadways to zero by 2030.
anchor

Fiscal Note

State aid totals $9.9 million. $1.5 million was approved in the FY22 Maryland General Assembly. $2.1 million was approved in each of the FY23, FY24, and FY25 General Assembly sessions. An additional $2.1 million of State aid is preauthorized by the General Assembly for FY26.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland State Highway Administration, Maryland-National Capital Park and Planning Commission, Department of Permitting Services, Greater Olney Civic Association (GOCA), and utility companies
Budget Snapshot
$30.33M Total
Expenditures/Funding
$25.99M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP502108
Date Last Modified01/11/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaUpper Rock Creek Watershed
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision7632174613854501971173517950000
Land1837101201626626000000
Site Improvements and Utilities16800016801680000000
Construction1917900191790921199680000
Other00000000000
Total Expenditures303281756258625986327710946117630000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds2041901262191572757674696540000
Intergovernmental90090090000
State Aid9900175613246820520420021000000
Total Funding Sources303281756258625986327710946117630000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance15---555
Energy3---111
NET IMPACT18---666
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request3276
Year First AppropriationFY23
Appropriation FY 28 Request22700
Last FY's Cost Estimate30328
Cumulative Appropriation4343
Expenditure / Encumbrances2245
Unencumbered Balance2098