up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the design and construction of bicycle and pedestrian capital improvements in the Veirs Mill Road/Randolph Road Bicycle-Pedestrian Priority Area (BiPPA) identified in County master plans with costs beyond FY23 incorporated into the Bus Rapid Transit: Veirs Mill Road (501913) project to maximize federal funding for the project.
anchor

Phase

Preliminary Design Stage

Status

Pending Closeout
anchor
Budget Snapshot
$3.5M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Preliminary design of projects in the Western Sector started in FY21 and continued in FY22. Preliminary design of projects in the Central and Eastern Sectors started in FY22. All preliminary design activities have been completed and final design is underway as part of the Veirs Mill Road BRT project.
anchor

Justification

This project will enhance efforts in other projects to improve pedestrian and bicyclist mobility, safety, and access in the Randolph/Veirs Mill BiPPA. These efforts will also help to meet master plan non-auto-driver mode share (NADMS) goals. The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030. This work will be coordinated with the Veirs Mill BRT project to minimize duplicative work and provide enhanced access to the BRT stations.
anchor

Fiscal Note

The original cost of this project was based on concept level estimates. The cost has been updated as design progressed and schedule accelerated to coincide with the Veirs Mill Road BRT project. This allows for this project to be included in the Capital Investment Grant (CIG) application to the Federal Transit Administration for the Veirs Mill Road BRT project.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland State Highway Administration, Maryland-National Capital Park & Planning Commission, Maryland Department of Natural Resources, Washington Metropolitan Area Transit Authority.
Budget Snapshot
$3.5M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502003
Date Last Modified11/09/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision3501679282200000000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures3501679282200000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds3419597282200000000
Impact Tax8282000000000
Total Funding Sources3501679282200000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY20
Appropriation FY 26 Request0
Last FY's Cost Estimate3501
Cumulative Appropriation3501
Expenditure / Encumbrances3434
Unencumbered Balance67