Description

This project will design and construct a new Bus Rapid Transit (BRT) line on Veirs Mill Road (MD 586) between the Wheaton Metro Station and Montgomery College in Rockville. Planning conducted by the Maryland Department of Transportation State Highway Administration (MDOT SHA) resulted in a Recommended Alternative in late 2017. The recommended alternative includes queue jumps for use by BRT and other buses at congested intersections along the corridor, new BRT stations with level boarding and off-board payment, Transit Signal Priority, purchase of new, zero-emission BRT buses, and other associated pedestrian and bicycle improvements along the corridor. The study retains curbside dedicated lanes as the long-term BRT alternative for Veirs Mill Road. In addition, MCDOT intends to accelerate the Veirs Mill and Randolph Road BiPPA project to provide expanded pedestrian and bicycle facilities along the corridor. The addition of a shared use path along the north side of Veirs Mill Road, completing sidewalk gaps along the south side, and improving pedestrian crossings along Veirs Mill Road will improve access to Flash stations.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$169.04M Total
Expenditures/Funding
$163.54M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Project planning was completed in FY18 and preliminary engineering was completed in FY22. Final design began in FY23 and will be completed by mid-FY25. Property acquisition activities will begin in FY24 and construction is anticipated to start in FY25 and be completed by FY27. Buses will be purchased in FY27.
anchor

Cost Change

Cost increase is due to the addition of the Veirs Mill Road/Randolph Road BiPPA project and updated project cost estimates from the 30% design stage. These costs include updates for unit cost increases to reflect inflation, year of expenditure, increased vehicle costs, and additional coordination with the Federal Transit Administration as part of the Federal Capital Investment Grant program.
anchor

Justification

The project will transform mobility options with the implementation of a seven-mile, premium, branded, limited-stop BRT service along Veirs Mill Road. This new service will improve transit travel time and increase opportunity for a broad range of users, including a significant number of minority and low-income riders living along a highly congested corridor. The project will improve passenger transit mobility by connecting riders to high density housing and employment centers. The incorporation of bicycle and pedestrian access and safety improvements will facilitate improved access to stations and improve overall corridor safety.

Plans & Studies: MCDOT Countywide Bus Rapid Transit Study, Final Report (July 2011); County Executive's Transit Task Force (May 2012); Countywide Transit Corridors Functional Master Plan (November 2013); Maryland Department of Transportation/Maryland State Highway Administration MD 586/Veirs Mill Road Draft Corridor Planning Study (September 2016); Veirs Mill Corridor Master Plan (April 2019).

anchor

Fiscal Note

The previous programming of funds for final design facilitated acceptance into the Federal Transit Administration's Capital Investment Grant (CIG) program. This project was combined with the Veirs Mill Road/Randolph Road BiPPA project to leverage additional Federal funds. The project was accepted in July 2022 into CIG Project Development and is now working toward a project rating and ultimately a funding grant agreement. The inclusion of the local portion of construction and bus purchase funding positions the project to advance through the CIG program in a timely fashion to receive a fully funded grant agreement. State Aid reflects state grants for capital projects in Montgomery County programmed and/or preauthorized during the 2022 and 2023 State General Assembly Sessions. The State Bus Rapid Transit Fund is a new source of annual funding available to BRT projects in Maryland, and funds shown from this source have been committed by the State to Montgomery County in 2023 and 2024.

anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland Department of Transportation, Washington Metropolitan Area Transit Authority, Maryland-National Capital Park and Planning Commission, City of Rockville, MDOT-SHA, Commission on People with Disabilities, Transit Advisory Group, Neighborhood and Civic Associations, and Veirs Mill Road BRT Corridor Advisory Committee, Federal Transit Administration
Download & Explore
Budget Snapshot
$169.04M Total
Expenditures/Funding
$163.54M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501913
Date Last Modified04/13/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision3334927052786278583500334842408385838500
Land133159013306064676833944103300
Site Improvements and Utilities1413800141380007069706900
Construction68760006876000252343523415600
Other39473003947300003947300
Total Expenditures169035271427861635353500399412175537509011600
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Current Revenue: Mass Transit92500250067500000675000
Federal Aid994470099447000223167713100
G.O. Bonds46700046700674922937213700
Impact Tax3000271428600000000
Op Lanes Maryland Transit Funding00000000000
State Aid23880002388035000020380000
State Bus Rapid Transit Fund287880028788033201125310117409800
Total Funding Sources169035271427861635353500399412175537509011600
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request0
Year First AppropriationFY20
Appropriation FY 24 Request35691
Last FY's Cost Estimate86800
Cumulative Appropriation9000
Expenditure / Encumbrances3275
Unencumbered Balance5725