up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for design, right-of-way acquisition, utility relocations, and construction of a new grade separated connection under Georgia Avenue to improve access to the Forest Glen Metro Station from neighborhoods and institutions located on the east side of Georgia Avenue. There is currently an underground walkway from the parking and bus area on the northwest quadrant of the intersection to the southwest quadrant. A new connection would be made to this passageway connecting the southwest quadrant to the northeast quadrant. A ramp connection and elevators bring the underground connection to grade on the northeast corner of the intersection. Associated sidewalk improvements would also be made to Forest Glen Road to complete the walking connection on the north side of the road to Holy Cross Hospital.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$18.47M Total
Expenditures/Funding
$18.47M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design will begin in FY21 and construction will begin in FY23.
anchor

Justification

This project is needed to improve the mobility, and safety for all facility users within the project area by reducing existing conflicts between pedestrians and vehicles. Currently, transit users, pedestrians, and bicyclists cross MD 97 (Georgia Avenue) and Forest Glen Road to access the Metro Station. This project will eliminate the need for these at-grade pedestrian crossings and will also facilitate crossing of the road for community members who are not using Metro. Traffic volumes and speeds on MD 97 can be very high and pedestrians must cross over eight lanes of traffic. These crossings can be very intimidating, reducing community connectivity and use of the Forest Glen Metro Station.The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County roadways to zero by 2030.
anchor

Fiscal Note

Construction costs are based on conceptual plans. and will be updated as design progresses.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Maryland-National Capital Park & Planning Commission, Maryland State Highway Administration, Washington Metropolitan Area Transit Authority.
Download & Explore
Budget Snapshot
$18.47M Total
Expenditures/Funding
$18.47M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501911
Date Last Modified03/03/20
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision41020041021252150045045045000
Land10000010000100000000
Site Improvements and Utilities130000130000650650000
Construction1207000120700030704500450000
Other00000000000
Total Expenditures1847200184721252250041705600495000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds1847200184721252250041705600495000
Total Funding Sources1847200184721252250041705600495000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request2752
Year First Appropriation
Appropriation FY 22 Request1000
Last FY's Cost Estimate18472
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0