up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the rehabilitation of the existing Brighton Dam Road Bridge No. M-0229 over Brighton Dam of Triadelphia Reservoir. This 602-foot long 15-span bridge, which is supported by Brighton Dam, is in need of repairs to the parapets, bridge deck joints, prestressed concrete beams, abutment backwalls, streetlights, and approach roadways and sidewalks to enhance the safety of the traveling public and the integrity of the dam. The existing storm inlets on the approach roadways at both ends of the bridge will be improved as needed. A new permanent turnaround site for fire trucks on the Howard County side will be constructed at the entrance to the existing WSSC Water maintenance yard, approximately 1,000 feet east of the bridge and next to the existing tanker fire truck water refill site. The existing diagonal crosswalk at the entrance of the Brighton Dam Azalea Garden on the Montgomery County side, approximately 320 feet west of the bridge, will be relocated to be perpendicular to Brighton Dam Road. An additional streetlight will be installed at each end of the relocated crosswalk.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$3.47M Total
Expenditures/Funding
$1.36M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

Upon completion, the Average Daily Traffic (ADT) on the Brighton Dam Road Bridge will remain approximately 6,000 vehicles per day.
anchor

Estimated Schedule

Design was completed 2023. Construction is scheduled to start in the spring of 2024 and be completed in the fall of 2024.
anchor

Cost Change

Cost increase is due to inflation and additional tasks including construction of a new turnaround site, relocation of the existing diagonal crosswalk and installation of additional streetlights at the relocated crosswalk.
anchor

Justification

This bridge, reconstructed in 1999, requires repairs to the 1,002-foot long west parapets, 642-foot long east parapets, sixteen bridge deck joints, prestressed concrete beams, abutment backwalls, street lights, and approach roadways and sidewalks. The parapets have severe concrete spalling at many parapet joints. Prestressed concrete beams and abutment backwalls have spalling and cracking. The approach roadways and sidewalks have settlement at both ends of the bridge. The bridge deck joints have failed, allowing water and deicing chemicals to flow through the bridge deck which resulted in corrosion and deterioration to the mechanized equipment for the dam operations. Some streetlights and pole supports are damaged. The bridge rehabilitation was requested by WSSC Water to protect the newly reconstructed dam operating equipment. The improvement of storm inlets was requested by WSSC Water to minimize storm runoff entering into the bridge deck surface from the approach roadways.
anchor

Other

The 2005 Olney Master Plan designates Brighton Dam Road as Arterial Road (A-15) with a minimum right-of-way of 80 feet. The December 2018 Montgomery County Bicycle Master Plan recommends bikeable shoulders. The deterioration of the bridge was identified through the County's 2021 biennial inspection program. The construction management and construction costs for the new fire truck turnaround site will be shared equally by Montgomery County and Howard County, and the remaining of the project costs will be shared equally by Montgomery County, Howard County and WSSC Water. WSSC Water will grant Howard County a perpetual maintenance easement for the new turnaround site at no cost. Streetlights, crosswalks, sidewalk ramps, bikeways, and other pertinent issues are included in the design of the project to ensure pedestrian safety.
anchor

Fiscal Note

The funding shown as "Intergovernmental" is from Howard County and WSSC Water for their share of the project cost.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

WSSC Water, Howard County, Maryland Department of the Environment, Maryland Department of Natural Resources, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Montgomery County Fire and Rescue Services, Montgomery County Police Department, Montgomery County Public Schools, Montgomery County Ride On Bus, Howard County Fire and Rescue Services, Howard County Police Department, Howard County Public Schools, Baltimore Gas and Electric Company, and U.S. Army Corps of Engineers.
Budget Snapshot
$3.47M Total
Expenditures/Funding
$1.36M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501907
Date Last Modified01/10/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaOlney and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision1292313648331331000000
Land00000000000
Site Improvements and Utilities00000000000
Construction21780115410241024000000
Other00000000000
Total Expenditures3470313180213551355000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds12850817468468000000
Intergovernmental2185313985887887000000
Total Funding Sources3470313180213551355000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request1220
Year First AppropriationFY19
Appropriation FY 26 Request0
Last FY's Cost Estimate2250
Cumulative Appropriation2250
Expenditure / Encumbrances462
Unencumbered Balance1788