up
Budget Year / Version:  
anchor
anchor
anchor

Description

Poolesville High School was built in 1953 and renovated in 1978. Scheduling of this modernization is consistent with the MCPS long-range plans to renew aging facilities on a rational and periodic basis. Due to fiscal constraints, the high school modernization program was delayed two years in the adopted FY 2013-2018 CIP. While planning funds remain on schedule, due to fiscal constraints, the construction funds for this project were delayed one year in the approved FY2015-2020 CIP. The Board of Education's requested FY2015-2020 Amended CIP reinstated the construction schedule previously requested by the Board. Due to fiscal constraints, the County Council did not approve the Board's request. Based on the Montgomery County Council Office of Legislative Oversight (OLO) study of the revitalization/expansion program released in July 2015, this program is under review in order to develop a multi-variable approach to determine the priority order of large-scale renovations of facilities, possibly including programmatic and capacity considerations. Recommendations regarding possible changes to this program will be released once the review is complete.
project image
anchor

Phase

Under Construction

Status

Closeout
anchor
Budget Snapshot
$0M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

Budget Snapshot
$0M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP136521
Date Last Modified05/16/23
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaPoolesville and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures00000000000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds00000000000
Total Funding Sources00000000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request-954
Year First AppropriationFY16
Appropriation FY 24 Request0
Last FY's Cost Estimate0
Cumulative Appropriation3818
Expenditure / Encumbrances0
Unencumbered Balance3818