anchor Description
Design and construction of this project will be performed in two parts: 4,000 feet of 24-inch diameter water main along Brink Road and Route 355 and 1,500 feet of 24-inch diameter water main along West Old Baltimore Road; and 2,400 feet of 24-inch diameter water main along West Old Baltimore Road.
anchor Justification
General plan and M-NCPP&PC Round 6 growth forecasts. This water main is planned to serve the area designated as Stage 3 in the Clarksburg Master Plan and Hyattstown Special Study Area, approved and adopted in June 1994.
anchorOther
The project scope was developed for the FY2011 CIP and has a total cost of $1,954. This project was previously part of WSSC Project W-46.14. Expenditures shown in Block B are planned level estimates only and may change depending on site-specific conditions and design constraints. Land costs are included in WSSC Project W-200.00.
anchorCoordination
Montgomery County Government, Maryland-National Capital Park & Planning Commission and WSSC Projects W-46.14, Clarksburg Area Stage 3 Water Main, Parts 1,2 & 3 and W-46.15, Clarksburg Elevated Water Storage Facility.